Plan Details

Status:
Approved
Type:
Map/Use Changes - Entitlements
Apply Date:
08/03/2022
Applicant:
Brian
Description:
SE-22-35 TEP - Cottonwood Lane - Special Exception Land Use request to allow a 138kV Tucson Electric Power substation on a vacant site totaling 10.7 acres with split zoning (9.4 acres of R-1 and 1.3 acres of R-2) with 12-foot high screen wall and 20-foot wide perimeter landscape border. - TEP 138 kV substation
Architects:
  • Tucson Electric Power
Contractors:

Plan Reviews

Plan Number - T22SE00035
Plan Status: Approved
Plan Description: SE-22-35 TEP - Cottonwood Lane - Special Exception Land Use request to allow a 138kV Tucson Electric Power substation on a vacant site totaling 10.7 acres with split zoning (9.4 acres of R-1 and 1.3 acres of R-2) with 12-foot high screen wall and 20-foot wide perimeter landscape border. - TEP 138 kV substation
Start Date Submittal Complete Date Status  
08/03/2022 REZONING - IPC 08/23/2022 COMPLETED Review Details
08/30/2022 REZONING - ZE HEARING 10/20/2022 ACTIVE Review Details