Plan: S19-012
Plan Details
Apply Date:
02/25/2019
Applicant:
Linda
Description:
LA ESTANCIA FINAL PLAT, BLK 26
Architects:
- City of Tucson DTM Streets and Traffic Maintenance
- Linda Thompson / The WLB Group, inc.
- MERITAGE HOMES CONSTRUCTION INC
- Title Security Agency, LLC, a Delaware limited liability com. trust 202065-S as trustee, Ronda Tatro
Contractors:
Outstanding Inspections
Permit Status:
Permit Number:
Permite Description:
Total Outstanding Inspections - 1
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/28/2022 | COT - ENGR - Site - Assurance Release | Partial Pass | {Activity date: 04/27/2022; Status: Partial Approval; Inspector: DROBERTS; Comment: Entered by DROBERT5 - PARTIAL APPROVAL OK FOR THE RELEASE OF LOT #17} ; {Activity date: 04/28/2022; Status: Partial Approval; Inspector: DROBERTS; Comment: Entered by DROBERT5 - PARTIAL APPROVAL, OK TO RELEASE LOT #14} ; {Activity date: 03/08/2022; Status: Approved; Inspector: DROBERTS; Comment: Entered by VVERA1 - APPROVED} ; {Activity date: 10/29/2021; Status: Partial Approval; Inspector: DROBERTS; Comment: Entered by DROBERT5 - IS PARTIAL OK TO RELEASE Lots 15 and 16.} ; {Activity date: 10/29/2021; Status: Continued; Inspector: DROBERTS; Comment: Entered by RSALDAT1 - CONTINUED, NO CONCERNS AT THIS TIME.} ; {Activity date: 11/25/2020; Status: Partial Approval; Inspector: RLEDONNE; Comment: Entered by PAHUMAD1 - Partial approval. OK for release of lot. #11} ; {Activity date: 11/19/2020; Status: Partial Approval; Inspector: RLEDONNE; Comment: Entered by PAHUMAD1 - partial approval. OK for lot releases for lots. 18,22 and 45.} ; {Activity date: 11/19/2020; Status: Partial Approval; Inspector: RLEDONNE; Comment: Entered by PAHUMAD1 - partial approval. OK for lot releases for lots. 18,22 and 45.} ; {Activity date: 10/30/2020; Status: Partial Approval; Inspector: DROBERTS; Comment: Entered by RSALDAT1 - THE FOLLOWING LOTS ARE OK FOR RELEASE 19,21,40,42,43,44,46 AND 47. THE FOLLOWING LOTS WITHIN THESE LOTS HAVE HAD SOME MINOR SEWER LINE ADJUSTMENTS SINCE THE PAVEMENT PLACEMENT WAS COMPLETE, 19, 21, 40, 44, 46,& 47} ; {Activity date: 10/30/2020; Status: Partial Approval; Inspector: DROBERTS; Comment: Entered by RSALDAT1 - THE FOLLOWING LOTS ARE OK FOR RELEASE 19,21,40,42,43,44,46 AND 47. THE FOLLOWING LOTS WITHIN THESE LOTS HAVE HAD SOME MINOR SEWER LINE ADJUSTMENTS SINCE THE PAVEMENT PLACEMENT WAS COMPLETE, 19, 21, 40, 44, 46,& 47} ; {Activity date: 10/28/2020; Status: Partial Approval; Inspector: RLEDONNE; Comment: Entered by RSALDAT1 - Partial approval. OK for Release of lot #40.} ; {Activity date: 10/27/2020; Status: Partial Approval; Inspector: RLEDONNE; Comment: Entered by RSALDAT1 - partial approval. OK for lot release # 20.} ; {Activity date: 09/28/2020; Status: Partial Approval; Inspector: RLEDONNE; Comment: Entered by JSCHNEI2 - Partial approval. OK for lot release #23.} ; {Activity date: 09/28/2020; Status: Partial Approval; Inspector: RLEDONNE; Comment: Entered by JSCHNEI2 - Partial approval. OK for lot release #23.} ; {Activity date: 09/03/2020; Status: Partial Approval; Inspector: RLEDONNE; Comment: Entered by JSCHNEI2 - partial approval. OK for release of lots.24,27,30,32,39,and 41. } ; {Activity date: 09/03/2020; Status: Partial Approval; Inspector: RLEDONNE; Comment: Entered by JSCHNEI2 - partial approval. OK for release of lots.24,27,30,32,39,and 41.} ; {Activity date: 08/14/2020; Status: Partial Approval; Inspector: RLEDONNE; Comment: Entered by RSALDAT1 - partial approval. OK for releases of lots. 1,2,3,4,25,26,28,29,31,33,34,35. } ; {Activity date: 07/24/2020; Status: Partial Approval; Inspector: DROBERTS; Comment: Entered by JSCHNEI2 - PARTIAL AT THIS TIME, OK TO RELEASE THE FOLLOWING LOTS 5,6,7,8,9,10,36,37, THE SIDEWALKS AND DRIVE WAYS WILL BE CHECKED AT A LATER DATE } ; {Activity date: 07/24/2020; Status: Partial Approval; Inspector: DROBERTS; Comment: Entered by JSCHNEI2 - PARTIAL AT THIS TIME, OK TO RELEASE THE FOLLOWING LOTS 5,6,7,8,9,10,36,37, THE SIDEWALKS AND DRIVE WAYS WILL BE CHECKED AT A LATER DATE} ; {Activity date: 07/17/2020; Status: Partial Approval; Inspector: RLEDONNE; Comment: Entered by RSALDAT1 - Partial approval. OK for releases of lot #7through #10. } |
Completed Inspections
Permit Status:
Permit Number:
Permit Description:
Total Completed Inspections - 3
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/21/2020 | SPECIAL INSPECTION - Pima County Sewer (Third Party) | Passed | {Activity date: 05/21/2020; Status: Approved; Inspector: JV; Comment: Entered by JVWINKL1 - See uploaded acceptance Letter G-2019-038} | |
06/03/2020 | COT - WATR - Design Plan Construction | Passed | {Activity date: 06/03/2020; Status: Approved; Inspector: JV; Comment: Entered by JVWINKL1 - See Tucson Water Final Acceptance 2-043-2019} | |
06/03/2020 | TRSP – PIA - Engineering Final – Completion of PIA Work (Final Lot Release/Acceptance) | Passed | {Activity date: 06/03/2020; Status: Approved; Inspector: RLEIGH; Comment: Entered by RLEIGH1 - } |
Plan Reviews
Plan Number - S19-012
Plan Status: Submitted
Plan Description: LA ESTANCIA FINAL PLAT, BLK 26
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/24/2019 | SUBPLAT- OK TO SUBMIT | 03/01/2019 | COMPLETED |
03/01/2019 | FINAL PLAT - REVIEW | 04/10/2019 | COMPLETED |
05/09/2019 | RESUBMITTAL - CDRC - FINAL PLAT REVIEW | 06/18/2019 | COMPLETED |
06/16/2020 | ASSURANCES | 06/23/2020 | COMPLETED |
06/28/2019 | FINAL PLAT - PACKAGE | 07/10/2019 | COMPLETED |
07/11/2019 | FINAL PLAT - PACKAGE | 07/12/2019 | COMPLETED |