Permit: TW-CONS-0326-0020
Permit Details
Status:
Inspections
Type:
TW CIP Planning & Engineering
Address:
3901 S CONTRACTORS WY
Address NEW:
3901 S CONTRACTORS WY
Apply Date:
03/31/2026
Applicant:
Andres Amado
Description:
Refinery Way 12-in Main Replacement. At the time of entering this project into EPL, the project is in construction. Abandonment work is underway; the jack and bore SOW is pending easement acquisition.
Outstanding Inspections
Permit Status: Inspections
Permit Number: TW-CONS-0326-0020
Permite Description: Refinery Way 12-in Main Replacement.
At the time of entering this project into EPL, the project is in construction. Abandonment work is underway; the jack and bore SOW is pending easement acquisition.
Total Outstanding Inspections - 2
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| TWPE Daily Field Inspection | N/A | Scheduled | ||
| TWPE Summary review of Daily Field Inspections | N/A | Scheduled |
Scheduled Inspections
Scheduled Inspections - TW-CONS-0326-0020
Status: Inspections
Description: Refinery Way 12-in Main Replacement.
At the time of entering this project into EPL, the project is in construction. Abandonment work is underway; the jack and bore SOW is pending easement acquisition.
| Scheduled Date | Description | Entered By | Entered Date |
|---|---|---|---|
| 05/25/2026 | TWPE Daily Field Inspection | Scheduled | |
| 05/25/2026 | TWPE Summary review of Daily Field Inspections | Scheduled |
For information about today’s scheduled inspections please refer to the