Permit Details

Status:
Inspections
Type:
Right-of-Way (ROW) - Utility
Address:
4701 N STONE AV
Address NEW:
4701 N STONE AV
Apply Date:
12/11/2025
Applicant:
John Rhodes
Description:
Tie in pointTie in point from Alternative splice case SP0049 That is currently being built.. From existing dog house south on Stone Ave crossing under River Rd. Then turn west under Stone Ave then south again. Install 5 vaults. Total bore 1860' 02/11/26- Renewal for 30 days as of 2/11/26 new expiration date is 03/13/26

Permit Reviews

Permit Number - TR-UTL-1225-02133
Permit Status: Inspections
Permit Description: Tie in pointTie in point from Alternative splice case SP0049 That is currently being built.. From existing dog house south on Stone Ave crossing under River Rd. Then turn west under Stone Ave then south again. Install 5 vaults. Total bore 1860' 02/11/26- Renewal for 30 days as of 2/11/26 new expiration date is 03/13/26
Start Date Submittal Complete Date Status  
01/26/2026 RIGHT-OF-WAY REVIEW REVISION v.2 01/26/2026 APPROVED Review Details
12/17/2025 RIGHT-OF-WAY REVIEW v.2 12/17/2025 APPROVED Review Details
12/12/2025 RIGHT-OF-WAY REVIEW v.1 12/15/2025 REQUIRES RESUBMIT Review Details
01/20/2026 RIGHT-OF-WAY REVIEW REVISION v.1 01/22/2026 REQUIRES RESUBMIT Review Details

Outstanding Activity Conditions

Permit Number - TR-UTL-1225-02133
Permit Status: Inspections
Permit Description: Tie in pointTie in point from Alternative splice case SP0049 That is currently being built.. From existing dog house south on Stone Ave crossing under River Rd. Then turn west under Stone Ave then south again. Install 5 vaults. Total bore 1860' 02/11/26- Renewal for 30 days as of 2/11/26 new expiration date is 03/13/26
Total Outstanding Activity Conditions - 5
Date Name
01/26/2026 Review Notes: 1) Additional TCP required for any impact to Pedestrian or Bike Lane Access. 2) Additional TCP required for impact to travel lanes during work or Potholing work.
12/15/2025 ** PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. ** PAVEMENT PATCH TYPE SHALL BE IN CONFORMANCE TO THE CURRENT EDITION OF THE CITY OF TUCSON PUBLIC UTILITY ADMINISTRTIVE MANUAL **Pedestrian Access & Sidewalk PEDESTRIAN ACCESS MUST BE PROVIDED AND MAINTIANED PER MUTCD CHAPTER 6D. FIELD ADJUSTMENTS MAY BE REQUIRED. REPLACE/REPAIR SIDEWALK PANELS PER PAG STANDARD DETAIL 200\206 . PEDESTRIAN DETOUR ROUTE ON SAME SIDE OF RIGHT OF WAY TO BE PROVIDED. PER CITY CODE AND POLICY. Refer to MUTCD Chapter 6 Figure 6P-28, and 6K figure 6K-2. Refer to COT Utility manual Page 41 - 42 Refer to COT 2015 Addition to the MUTCD section 14
12/15/2025 Bus stop in the area, contact Joe Garcia, Sun Tran Dispatch, at 520-576-8726 at least 48-business hours prior to start of work for coordination
12/15/2025 Traffic control set-up approved between 9AM - 3:30PM
12/17/2025 Private Property Driveways and private property shall NOT be utilized without the owner’s consent. It is the contractor’s responsibility to negotiate use of private property.

Outstanding Inspections

Permit Status: Inspections
Permit Number: TR-UTL-1225-02133
Permite Description: Tie in pointTie in point from Alternative splice case SP0049 That is currently being built.. From existing dog house south on Stone Ave crossing under River Rd. Then turn west under Stone Ave then south again. Install 5 vaults. Total bore 1860' 02/11/26- Renewal for 30 days as of 2/11/26 new expiration date is 03/13/26
Total Outstanding Inspections - 3
Last Inspection Date Description Inspector Results Comments
TRSP - ROW - Barricade - Setup/Routine N/A Requested
TRSP - ROW - Backfill - Placement/Compaction N/A Requested
TRSP - ROW - Final N/A Requested

Completed Inspections

Permit Status: Inspections
Permit Number: TR-UTL-1225-02133
Permit Description: Tie in pointTie in point from Alternative splice case SP0049 That is currently being built.. From existing dog house south on Stone Ave crossing under River Rd. Then turn west under Stone Ave then south again. Install 5 vaults. Total bore 1860' 02/11/26- Renewal for 30 days as of 2/11/26 new expiration date is 03/13/26
Total Completed Inspections - 1
Date Description Inspector Results Comments
01/15/2026 TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting Passed

Documents

File Name Document Type  
COT - TR - ROW PERMIT (SSRS).PDF DOCUMENTS VIEW
COT - TR - ROW PERMIT (SSRS).PDF DOCUMENTS VIEW
JB0002405994_PERMIT MAP_V1.PDF DOCUMENTS VIEW
TCP 2_V2.PDF DOCUMENTS VIEW