Permit: TR-UTL-1225-02124
Permit Details
Status:
Inspections
Type:
Right-of-Way (ROW) - Utility
Address:
2402 S FORGEUS SV
Address NEW:
2402 S FORGEUS SV
Apply Date:
12/10/2025
Applicant:
Matthew Lorefice
Description:
CONTINUATION OF Remove and Replace existing 4in ACP Sewer Main with 6" PVC. Replace Cleanout with a Terminal MH
Permit Reviews
Permit Number - TR-UTL-1225-02124
Permit Status: Inspections
Permit Description: CONTINUATION OF Remove and Replace existing 4in ACP Sewer Main with 6" PVC.
Replace Cleanout with a Terminal MH
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 12/10/2025 | RIGHT-OF-WAY REVIEW v.1 | 12/15/2025 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-UTL-1225-02124
Permit Status: Inspections
Permit Description: CONTINUATION OF Remove and Replace existing 4in ACP Sewer Main with 6" PVC.
Replace Cleanout with a Terminal MH
Total Outstanding Activity Conditions - 3
| Date | Name |
|---|---|
| 12/12/2025 | PRE-CON/SIDEWALK |
| 12/12/2025 | Traffic Control set-up approved between 7AM - 5PM |
| 12/15/2025 | Pavement Patch type Shall Be in conformance to the current edition of the City of Tucson Public Utility Administrative Manual. |
Outstanding Inspections
Permit Status: Inspections
Permit Number: TR-UTL-1225-02124
Permite Description: CONTINUATION OF Remove and Replace existing 4in ACP Sewer Main with 6" PVC.
Replace Cleanout with a Terminal MH
Total Outstanding Inspections - 2
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/26/2026 | TRSP - ROW - Backfill - Placement/Compaction | N/A | Re-inspection required | |
| 02/26/2026 | TRSP - ROW - Final | N/A | Re-inspection required |
Completed Inspections
Permit Status: Inspections
Permit Number: TR-UTL-1225-02124
Permit Description: CONTINUATION OF Remove and Replace existing 4in ACP Sewer Main with 6" PVC.
Replace Cleanout with a Terminal MH
Total Completed Inspections - 1
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/26/2026 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed |