Permit: TR-UTL-1224-02404
Permit Details
Status:
Complete
Type:
Right-of-Way (ROW) - Utility
Address:
6530 E TANQUE VERDE RD
Address NEW:
6530 E TANQUE VERDE RD
Apply Date:
12/20/2024
Applicant:
Ben Lozano / Border Traffic Safety LLC
Description:
Installing 4" fire protection service
Permit Reviews
Permit Number - TR-UTL-1224-02404
Permit Status: Complete
Permit Description: Installing 4" fire protection service
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 12/22/2024 | RIGHT-OF-WAY REVIEW v.1 | 12/26/2024 | REQUIRES RESUBMIT |
| 01/03/2025 | RIGHT-OF-WAY REVIEW v.3 | 01/07/2025 | APPROVED |
| 01/02/2025 | RIGHT-OF-WAY REVIEW v.2 | 01/02/2025 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TR-UTL-1224-02404
Permit Status: Complete
Permit Description: Installing 4" fire protection service
Total Outstanding Activity Conditions - 4
| Date | Name |
|---|---|
| 01/17/2025 | The following extended traffic control set-up times were approved: |
| 12/26/2024 | ** PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. ** PAVEMENT PATCH TYPE SHALL BE IN CONFORMANCE TO THE CURRENT EDITION OF THE CITY OF TUCSON PUBLIC UTILITY ADMINISTRTIVE MANUAL **SIDEWALK CLOSED AHEAD SIGNS SHALL BE PLACED AT THE NEAREST ADA ACCESS RAMPS PER MUTCD CHAPTER 6D. |
| 12/26/2024 | Traffic control set-up approved between 9AM - 3:30PM |
| 12/26/2024 | A NOTICE OF TEMPORARY HOLIDAY RESTRICTION applies to this permit and will be in effect from Thanksgiving Day to January 02. Due to the increasing traffic volume on many of the City’s roads, it is necessary to restrict lane closures on certain roads during the holiday season. |
Completed Inspections
Permit Status: Complete
Permit Number: TR-UTL-1224-02404
Permit Description: Installing 4" fire protection service
Total Completed Inspections - 5
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/17/2025 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | ||
| 01/22/2025 | TRSP - ROW - Backfill - Placement/Compaction | Passed | ||
| 02/07/2025 | TRSP - ROW - Barricade - Setup/Routine | Passed | ||
| 02/21/2025 | TRSP - ROW - Concrete - Acceptance (Post-Pour) | Passed | ||
| 05/01/2025 | TRSP - ROW - Final | Passed |