Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: TR-UTL-1224-02369
Permit Details
Apply Date:
12/17/2024
Applicant:
Desert Barricades LLC
Description:
Emergency 12/22/2024 - WO T136004 - TEP to replace 415’ of damaged fiber in utility vaults and existing ducts. No excavation is required.
Permit Reviews
Permit Number - TR-UTL-1224-02369
Permit Status: Issued
Permit Description: Emergency 12/22/2024 - WO T136004 - TEP to replace 415’ of damaged fiber in utility vaults and existing ducts. No excavation is required.
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
12/17/2024 | RIGHT-OF-WAY REVIEW v.1 | 12/20/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-UTL-1224-02369
Permit Status: Issued
Permit Description: Emergency 12/22/2024 - WO T136004 - TEP to replace 415’ of damaged fiber in utility vaults and existing ducts. No excavation is required.
Total Outstanding Activity Conditions - 4
Date | Name |
---|---|
12/18/2024 | This project is located in an Archaeological Sensitivity Zone. An Archaeological Monitor hired by the permit applicant is required to be on-site during any digging, unless a waiver is issued. Monitoring reports are to be submitted to Historic Preservation Office, City of Tucson, P.O. Box 27210, Tucson, AZ 85726.** Please contact Historic Preservation Office at PDSDHistoric@tucsonaz.gov. |
12/18/2024 | ** PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. ** PAVEMENT PATCH TYPE SHALL BE IN CONFORMANCE TO THE CURRENT EDITION OF THE CITY OF TUCSON PUBLIC UTILITY ADMINISTRTIVE MANUAL **SIDEWALK CLOSED AHEAD SIGNS SHALL BE PLACED AT THE NEAREST ADA ACCESS RAMPS PER MUTCD CHAPTER 6D. |
12/19/2024 | DTM has approved Tucson Electric Power work for 1 day Only on 12/22/2024, during scheduled Power Outage. Any and all additional work will need to be scheduled for completion after Holiday Restriction have been lifted on 1/02/2025. |
12/19/2024 | The following extended traffic control set-up times were approved: |