Permit: TR-UTL-1126-01903
Permit Details
Status:
Needs Resubmittal
Type:
Right-of-Way (ROW) - Utility
Address:
115 N EUCLID AV
Address NEW:
115 N EUCLID AV
Apply Date:
11/03/2026
Applicant:
Aidan Willis
Description:
Zayo (ADB Companies) to install conduit/fiber along City of Tucson ROW for an estimated 5,024 LF. Zayo Handholes to be installed every 2,000 LF. New Permit submittal for expired permit TR-UTL-0626-00949
Permit Reviews
Permit Number - TR-UTL-1126-01903
Permit Status: Needs resubmittal
Permit Description: Zayo (ADB Companies) to install conduit/fiber along City of Tucson ROW for an estimated 5,024 LF. Zayo Handholes to be installed every 2,000 LF. New Permit submittal for expired permit TR-UTL-0626-00949
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 11/04/2026 | RIGHT-OF-WAY REVIEW v.1 | 11/16/2026 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TR-UTL-1126-01903
Permit Status: Needs resubmittal
Permit Description: Zayo (ADB Companies) to install conduit/fiber along City of Tucson ROW for an estimated 5,024 LF. Zayo Handholes to be installed every 2,000 LF. New Permit submittal for expired permit TR-UTL-0626-00949
Total Outstanding Activity Conditions - 6
| Date | Name |
|---|---|
| 11/06/2026 | 3RD AVE IS UNDER A PAVEMENT MORATORIUM, ANY NEW ASPHALT THAT IS DISTURBED WILL REQUIRE A 2” MILL AND OVERLAY FOR 25’ IN EACH DIRECTION FROM THE OUTSIDE OF THE CUT FOR ALL EFFECTED TRAVEL LANES. |
| 11/06/2026 | Traffic control set-up approved between 9AM - 3:30PM |
| 11/06/2026 | Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area. |
| 11/06/2026 | PEDESTRIAN ACCESS MUST BE PROVIDED AND MAINTIANED PER MUTCD CHAPTER 6D. FIELD ADJUSTMENTS MAY BE REQUIRED. REPLACE/REPAIR SIDEWALK PANELS PER PAG STANDARD DETAIL 200\206 . SIDEWALK CLOSED AHEAD SIGNS SHALL BE PLACED AT THE NEAREST ADA ACCESS RAMPS IF LOCATED WITHIN 660' OF CLOSURE. PEDESTRIAN DETOUR ROUTE ON SAME SIDE OF RIGHT OF WAY TO BE PROVIDED IF NO ADA RAMPS ACCESSABLE. |
| 11/06/2026 | Pre- activity/construction meeting with City inspectors to be held 72 hours in advance of work start. Please request Inspections in your permit portal on TDC Online. |
| 11/06/2026 | PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. |