Permit: TR-UTL-1125-01971
Permit Details
Status:
Inspections
Type:
Right-of-Way (ROW) - Utility
Address:
3682 E MARCH PL
Address NEW:
3682 E MARCH PL
Apply Date:
11/13/2025
Applicant:
Adrien Pineda
Description:
ARIZONA PIPELINE WILL NEED TO EXCAVATE (1)5'X5' BELL HOLE IN ASPHALT ALLEY IN ORDER TO REPLACE THE GAS SERVICE FOR 3682 E MARCH PL
Permit Reviews
Permit Number - TR-UTL-1125-01971
Permit Status: Inspections
Permit Description: ARIZONA PIPELINE WILL NEED TO EXCAVATE (1)5'X5' BELL HOLE IN ASPHALT ALLEY IN ORDER TO REPLACE THE GAS SERVICE FOR 3682 E MARCH PL
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 11/13/2025 | RIGHT-OF-WAY REVIEW v.1 | 11/13/2025 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-UTL-1125-01971
Permit Status: Inspections
Permit Description: ARIZONA PIPELINE WILL NEED TO EXCAVATE (1)5'X5' BELL HOLE IN ASPHALT ALLEY IN ORDER TO REPLACE THE GAS SERVICE FOR 3682 E MARCH PL
Total Outstanding Activity Conditions - 4
| Date | Name |
|---|---|
| 11/13/2025 | Your project work requires that you contact City of Tucson Environmental Services Department (520-791-3171) at least 24 hours prior to closing any street or alley. |
| 11/13/2025 | ** PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. ** PAVEMENT PATCH TYPE SHALL BE IN CONFORMANCE TO THE CURRENT EDITION OF THE CITY OF TUCSON PUBLIC UTILITY ADMINISTRTIVE MANUAL **Pedestrian Access & Sidewalk PEDESTRIAN ACCESS MUST BE PROVIDED AND MAINTIANED PER MUTCD CHAPTER 6D. FIELD ADJUSTMENTS MAY BE REQUIRED. REPLACE/REPAIR SIDEWALK PANELS PER PAG STANDARD DETAIL 200\206 . PEDESTRIAN DETOUR ROUTE ON SAME SIDE OF RIGHT OF WAY TO BE PROVIDED. PER CITY CODE AND POLICY. Refer to MUTCD Chapter 6 Figure 6P-28, and 6K figure 6K-2. Refer to COT Utility manual Page 41 - 42 Refer to COT 2015 Addition to the MUTCD section 14 |
| 11/13/2025 | PAVEMENT MORATORIUM: ANY NEW ASPHALT THAT IS DISTURBED WILL REQUIRE A 2” MILL AND OVERLAY FOR 25’ IN EACH DIRECTION FROM THE OUTSIDE OF THE CUT FOR ALL EFFECTED TRAVEL LANES. |
| 11/13/2025 | Traffic Control set-up approved between 7AM - 5PM |
Outstanding Inspections
Permit Status: Inspections
Permit Number: TR-UTL-1125-01971
Permite Description: ARIZONA PIPELINE WILL NEED TO EXCAVATE (1)5'X5' BELL HOLE IN ASPHALT ALLEY IN ORDER TO REPLACE THE GAS SERVICE FOR 3682 E MARCH PL
Total Outstanding Inspections - 1
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/14/2026 | TRSP - ROW - Final | N/A | Re-inspection required | Work appears to be complete but cold mix patches already starting to sink and fail. There’s also still traffic control present in the alley. There is also dirt and cold mix that needs to be removed. |
Completed Inspections
Permit Status: Inspections
Permit Number: TR-UTL-1125-01971
Permit Description: ARIZONA PIPELINE WILL NEED TO EXCAVATE (1)5'X5' BELL HOLE IN ASPHALT ALLEY IN ORDER TO REPLACE THE GAS SERVICE FOR 3682 E MARCH PL
Total Completed Inspections - 3
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/21/2025 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | The site is ready to begin work. Arizona pipeline is well aware of the city of Tucson specifications and requirements for work within the right of way. | |
| 01/14/2026 | TRSP - ROW - Barricade - Setup/Routine | Passed | Traffic control meets standards | |
| 01/14/2026 | TRSP - ROW - Backfill - Placement/Compaction | Passed | Work is complete and backfill is sufficient |