Permit: TR-UTL-1124-02182
Permit Details
Status:
Complete
Type:
Right-of-Way (ROW) - Utility
Address:
8300 E TANQUE VERDE RD
Address NEW:
8300 E TANQUE VERDE RD
Apply Date:
11/18/2024
Applicant:
Eric Wieduwilt
Description:
Public sewer improvements. Installing 3,740lf of new sewer line and manholes along the south side of E. Tanque Verde Rd. with two sections crossing the road from the North side of E. Tanque Verde Rd. to South side of E. Tanque Verde Rd. -Workdays - Monday through Friday -Work Hours - 7am to 3pm -Work Duration - 3 months (Crossings to take 2 weeks each including patchback of asphalt) (Remainder of work on south side of E. Tanque Verde Rd. to take 2 months) -Work on south side of E. Tanque Verde Rd. to primarily use shoulder/bike lane closures as shown in TCP, right lane closure to be used only if necessary -Work crossing from north to south on both the maximum west and east ends of the project to use a combination of a right lane closure then a "football setup" to completes the crossing in a 4-step process (right lane closure for southern east bound lane, "football" for northern east bound lane the median and the southern west bound lane, right lane closure for northern west bound lane) -Nights/Variable hours of work for major crossing can be accepted in order to comply with COTDOT needs if needed 05/05/2025 DENIED – DUE TO THE APPLICANT APPLYING AFTER THE EXPIRATION DATE. APPLY FOR NEW PERMIT TO CONTINUE WORK.
Permit Reviews
Permit Number - TR-UTL-1124-02182
Permit Status: Complete
Permit Description:
Public sewer improvements. Installing 3,740lf of new sewer line and manholes along the south side of E. Tanque Verde Rd. with two sections crossing the road from the North side of E. Tanque Verde Rd. to South side of E. Tanque Verde Rd. -Workdays - Monday through Friday
-Work Hours - 7am to 3pm
-Work Duration - 3 months (Crossings to take 2 weeks each including patchback of asphalt) (Remainder of work on south side of E. Tanque Verde Rd. to take 2 months)
-Work on south side of E. Tanque Verde Rd. to primarily use shoulder/bike lane closures as shown in TCP, right lane closure to be used only if necessary
-Work crossing from north to south on both the maximum west and east ends of the project to use a combination of a right lane closure then a "football setup" to completes the crossing in a 4-step process (right lane closure for southern east bound lane, "football" for northern east bound lane the median and the southern west bound lane, right lane closure for northern west bound lane)
-Nights/Variable hours of work for major crossing can be accepted in order to comply with COTDOT needs if needed
05/05/2025 DENIED – DUE TO THE APPLICANT APPLYING AFTER THE EXPIRATION DATE. APPLY FOR NEW PERMIT TO CONTINUE WORK.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 11/18/2024 | RIGHT-OF-WAY REVIEW v.1 | 12/16/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-UTL-1124-02182
Permit Status: Complete
Permit Description:
Public sewer improvements. Installing 3,740lf of new sewer line and manholes along the south side of E. Tanque Verde Rd. with two sections crossing the road from the North side of E. Tanque Verde Rd. to South side of E. Tanque Verde Rd. -Workdays - Monday through Friday
-Work Hours - 7am to 3pm
-Work Duration - 3 months (Crossings to take 2 weeks each including patchback of asphalt) (Remainder of work on south side of E. Tanque Verde Rd. to take 2 months)
-Work on south side of E. Tanque Verde Rd. to primarily use shoulder/bike lane closures as shown in TCP, right lane closure to be used only if necessary
-Work crossing from north to south on both the maximum west and east ends of the project to use a combination of a right lane closure then a "football setup" to completes the crossing in a 4-step process (right lane closure for southern east bound lane, "football" for northern east bound lane the median and the southern west bound lane, right lane closure for northern west bound lane)
-Nights/Variable hours of work for major crossing can be accepted in order to comply with COTDOT needs if needed
05/05/2025 DENIED – DUE TO THE APPLICANT APPLYING AFTER THE EXPIRATION DATE. APPLY FOR NEW PERMIT TO CONTINUE WORK.
Total Outstanding Activity Conditions - 6
| Date | Name |
|---|---|
| 11/18/2024 | PRE-CON/PAVEMENT/SIDEWALK |
| 11/18/2024 | Traffic control set-up approved between 9AM - 3:30PM |
| 11/18/2024 | Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area. |
| 12/16/2024 | The following extended traffic control set-up times were approved: 24 hours |
| 12/16/2024 | Night work |
| 12/16/2024 | Prior to disturbing COT owned irrigation Contact Eric Ross at Eric.Ross@tucsonaz.gov Prior to disturbing any landscaping/vegetation in the right-of-way Contact David Marhefka at (520) 403-5074 david.marhefka@tucsonaz.gov |
Completed Inspections
Permit Status: Complete
Permit Number: TR-UTL-1124-02182
Permit Description:
Public sewer improvements. Installing 3,740lf of new sewer line and manholes along the south side of E. Tanque Verde Rd. with two sections crossing the road from the North side of E. Tanque Verde Rd. to South side of E. Tanque Verde Rd. -Workdays - Monday through Friday
-Work Hours - 7am to 3pm
-Work Duration - 3 months (Crossings to take 2 weeks each including patchback of asphalt) (Remainder of work on south side of E. Tanque Verde Rd. to take 2 months)
-Work on south side of E. Tanque Verde Rd. to primarily use shoulder/bike lane closures as shown in TCP, right lane closure to be used only if necessary
-Work crossing from north to south on both the maximum west and east ends of the project to use a combination of a right lane closure then a "football setup" to completes the crossing in a 4-step process (right lane closure for southern east bound lane, "football" for northern east bound lane the median and the southern west bound lane, right lane closure for northern west bound lane)
-Nights/Variable hours of work for major crossing can be accepted in order to comply with COTDOT needs if needed
05/05/2025 DENIED – DUE TO THE APPLICANT APPLYING AFTER THE EXPIRATION DATE. APPLY FOR NEW PERMIT TO CONTINUE WORK.
Total Completed Inspections - 4
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/09/2025 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | ||
| 04/09/2025 | TRSP - ROW - Backfill - Placement/Compaction | Passed | ||
| 04/09/2025 | TRSP - ROW - Final | Passed | ||
| 04/09/2025 | TRSP - ROW - Concrete - Subgrade/Forms (Pre-Pour) | Passed |