Permit Details

Status:
In Review
Type:
Right-of-Way (ROW) - Utility
Address:
2807 E 22ND ST
Address NEW:
2807 E 22ND ST
Apply Date:
10/29/2026
Applicant:
Arnulfo Quiroz
Description:
T178667 - Continuation of permit TR-UTL-0726-01086. The only work completed on the last permit was that holes were dug. Treat Ave. from 22nd St to 17th St, TEP will be replacing 15 poles, install 3 new poles, and 2 new Poly Pedestals in the ROW. TEP will also be replacing existing overhead wire.

Permit Reviews

Permit Number - TR-UTL-1026-01880
Permit Status: In review
Permit Description: T178667 - Continuation of permit TR-UTL-0726-01086. The only work completed on the last permit was that holes were dug. Treat Ave. from 22nd St to 17th St, TEP will be replacing 15 poles, install 3 new poles, and 2 new Poly Pedestals in the ROW. TEP will also be replacing existing overhead wire.
Start Date Submittal Complete Date Status  
10/30/2026 RIGHT-OF-WAY REVIEW v.1 N/A IN REVIEW Review Details

Outstanding Activity Conditions

Permit Number - TR-UTL-1026-01880
Permit Status: In review
Permit Description: T178667 - Continuation of permit TR-UTL-0726-01086. The only work completed on the last permit was that holes were dug. Treat Ave. from 22nd St to 17th St, TEP will be replacing 15 poles, install 3 new poles, and 2 new Poly Pedestals in the ROW. TEP will also be replacing existing overhead wire.
Total Outstanding Activity Conditions - 5
Date Name
11/02/2026 Notify in writing at least 5 working days before work begins, any businesses, residences and public transit routes affected by your temporary traffic control. PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING.
11/02/2026 Adjacent streets of work area are subject to a pavement moratorium. Any disturbance of existing asphalt will require pavement restoration in accordance with the current City of Tucson Public Utility Administrative Manual. A 2-inch mill and overlay covering one-half the width of the roadway shall be required. The final pavement restoration limits shall be confirmed by the ROW inspector at the preconstruction meeting.
11/02/2026 Traffic Control set-up approved between 7AM - 5PM
11/02/2026 PEDESTRIAN ACCESS MUST BE PROVIDED AND MAINTIANED PER MUTCD CHAPTER 6D. FIELD ADJUSTMENTS MAY BE REQUIRED. REPLACE/REPAIR SIDEWALK PANELS PER PAG STANDARD DETAIL 200\206 . PEDESTRIAN DETOUR ROUTE ON SAME SIDE OF RIGHT OF WAY TO BE PROVIDED. PER CITY CODE AND POLICY. Refer to MUTCD Chapter 6 Figure 6P-28, and 6K figure 6K-2. Refer to COT Utility manual Page 41 – 42 Refer to COT 2015 Addition to the MUTCD section 14
11/02/2026 Pre- activity/construction meeting with City inspectors to be held 72 hours in advance of work start. Please request Inspections in your permit portal by logging into tdc-online.tucsonaz.gov