Permit: TR-UTL-1026-01796
Permit Details
Apply Date:
10/16/2026
Applicant:
Alex Dietz
Description:
JO 326X015 Sites 1 and 2 - Site 1: Remove cleanout 2753*04 and install new terminal manhole to allow the installation of Approximately 150 LF of 8" Cured in Place Pipe between the new terminal manhole and MH 2753-05. Site 2: Remove cleanout 2753*05 and install new terminal manhole to allow the installation of approximately 150 LF of 8" Cured in Place Pipe between the new terminal manhole and MH 2753-06. Rehab entire MH bench for MH 2753-05 and 2753-06 per PCRWRD Standard Specifications and Details for Construction Std. 302. Install concrete collars on MH 2753-05 and MH 2753-06 per PCRWRD Standard Specifications and Details for Construction Std. 211.
Permit Reviews
Permit Number - TR-UTL-1026-01796
Permit Status: Issued
Permit Description: JO 326X015 Sites 1 and 2 - Site 1: Remove cleanout 2753*04 and install new terminal manhole to allow the installation of Approximately 150 LF of 8" Cured in Place Pipe between the new terminal manhole and MH 2753-05. Site 2: Remove cleanout 2753*05 and install new terminal manhole to allow the installation of approximately 150 LF of 8" Cured in Place Pipe between the new terminal manhole and MH 2753-06. Rehab entire MH bench for MH 2753-05 and 2753-06 per PCRWRD Standard Specifications and Details for Construction Std. 302. Install concrete collars on MH 2753-05 and MH 2753-06 per PCRWRD Standard Specifications and Details for Construction Std. 211.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 10/19/2026 | RIGHT-OF-WAY REVIEW v.1 | 10/23/2026 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-UTL-1026-01796
Permit Status: Issued
Permit Description: JO 326X015 Sites 1 and 2 - Site 1: Remove cleanout 2753*04 and install new terminal manhole to allow the installation of Approximately 150 LF of 8" Cured in Place Pipe between the new terminal manhole and MH 2753-05. Site 2: Remove cleanout 2753*05 and install new terminal manhole to allow the installation of approximately 150 LF of 8" Cured in Place Pipe between the new terminal manhole and MH 2753-06. Rehab entire MH bench for MH 2753-05 and 2753-06 per PCRWRD Standard Specifications and Details for Construction Std. 302. Install concrete collars on MH 2753-05 and MH 2753-06 per PCRWRD Standard Specifications and Details for Construction Std. 211.
Total Outstanding Activity Conditions - 6
| Date | Name |
|---|---|
| 10/20/2026 | Notify in writing at least 5 working days before work begins, any businesses, residences and public transit routes affected by your temporary traffic control. PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. |
| 10/20/2026 | Pre- activity/construction meeting with City inspectors to be held 72 hours in advance of work start. Please request Inspections in your permit portal on TDC Online. |
| 10/20/2026 | Traffic Control set-up approved between 7AM - 5PM |
| 10/22/2026 | Lane closures shall only be permitted during active work operations. At the end of each workday, the contractor shall remove all traffic control devices and reopen the roadway, bike lanes, and sidewalks to normal operation. Twenty-four (24) hour lane closures are not permitted unless specifically approved by the City. Traffic Control Devices shall not be stored in the bike lane or sidewalk |
| 10/22/2026 | Private Property Driveways and private property shall NOT be utilized without the owner’s consent. It is the contractor’s responsibility to negotiate use of private property. |
| 10/22/2026 | Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area. |