Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Issued
Type:
Right-of-Way (ROW) - Utility
Apply Date:
10/30/2023
Applicant:
ANGEL MORALES
Description:
P.090269 (KAHNA) - BORE 2,383' & TRENCH 7' TO PLACE CTL CONDUIT & FIBER. PLACE (3) CABINET/HANDHOLE/PEDESTALS 3/12/2024 Revision: Traffic Control plans for TR-UTL-1023-02825 / CenturyLink Job # P.090269. Bore has been relocated and some aerial work has been removed; specifics SHEET 5: Bore location and length changed to North of E 26th St and on the East of S Craycroft Rd, SHEET 7: Removed aerial work, SHEET 8: Removed aerial work & this sheet from package since work was removed

Permit Reviews

Permit Number - TR-UTL-1023-02825
Permit Status: Issued
Permit Description: P.090269 (KAHNA) - BORE 2,383' & TRENCH 7' TO PLACE CTL CONDUIT & FIBER. PLACE (3) CABINET/HANDHOLE/PEDESTALS 3/12/2024 Revision: Traffic Control plans for TR-UTL-1023-02825 / CenturyLink Job # P.090269. Bore has been relocated and some aerial work has been removed; specifics SHEET 5: Bore location and length changed to North of E 26th St and on the East of S Craycroft Rd, SHEET 7: Removed aerial work, SHEET 8: Removed aerial work & this sheet from package since work was removed
Start Date Submittal Complete Date Status  
02/23/2024 RIGHT-OF-WAY REVIEW v.1 02/27/2024 APPROVED Review Details
10/30/2023 RIGHT-OF-WAY REVIEW v.1 11/08/2023 REQUIRES RESUBMIT Review Details
03/11/2024 RIGHT-OF-WAY REVIEW v.1 03/13/2024 APPROVED Review Details
12/28/2023 RIGHT-OF-WAY REVIEW v.3 01/02/2024 APPROVED Review Details
12/20/2023 RIGHT-OF-WAY REVIEW v.2 12/21/2023 REQUIRES RESUBMIT Review Details

Outstanding Activity Conditions

Permit Number - TR-UTL-1023-02825
Permit Status: Issued
Permit Description: P.090269 (KAHNA) - BORE 2,383' & TRENCH 7' TO PLACE CTL CONDUIT & FIBER. PLACE (3) CABINET/HANDHOLE/PEDESTALS 3/12/2024 Revision: Traffic Control plans for TR-UTL-1023-02825 / CenturyLink Job # P.090269. Bore has been relocated and some aerial work has been removed; specifics SHEET 5: Bore location and length changed to North of E 26th St and on the East of S Craycroft Rd, SHEET 7: Removed aerial work, SHEET 8: Removed aerial work & this sheet from package since work was removed
Total Outstanding Activity Conditions - 2
Date Name
10/31/2023 ** PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. ** PAVEMENT PATCH TYPE SHALL BE IN CONFORMANCE TO THE CURRENT EDITION OF THE CITY OF TUCSON PUBLIC UTILITY ADMINISTRATIVE MANUAL. **SIDEWALK CLOSED AHEAD SIGNS SHALL BE PLACED AT THE NEAREST ADA ACCESS RAMPS PER MUTCD CHAPTER 6D.
10/31/2023 Traffic control set-up approved between 9AM - 3:30PM

Outstanding Inspections

Permit Status: Issued
Permit Number: TR-UTL-1023-02825
Permite Description: P.090269 (KAHNA) - BORE 2,383' & TRENCH 7' TO PLACE CTL CONDUIT & FIBER. PLACE (3) CABINET/HANDHOLE/PEDESTALS 3/12/2024 Revision: Traffic Control plans for TR-UTL-1023-02825 / CenturyLink Job # P.090269. Bore has been relocated and some aerial work has been removed; specifics SHEET 5: Bore location and length changed to North of E 26th St and on the East of S Craycroft Rd, SHEET 7: Removed aerial work, SHEET 8: Removed aerial work & this sheet from package since work was removed
Total Outstanding Inspections - 1
Last Inspection Date Description Inspector Results Comments
02/20/2024 TRSP - ROW - Backfill - Placement/Compaction N/A Re-inspection required

Completed Inspections

Permit Status: Issued
Permit Number: TR-UTL-1023-02825
Permit Description: P.090269 (KAHNA) - BORE 2,383' & TRENCH 7' TO PLACE CTL CONDUIT & FIBER. PLACE (3) CABINET/HANDHOLE/PEDESTALS 3/12/2024 Revision: Traffic Control plans for TR-UTL-1023-02825 / CenturyLink Job # P.090269. Bore has been relocated and some aerial work has been removed; specifics SHEET 5: Bore location and length changed to North of E 26th St and on the East of S Craycroft Rd, SHEET 7: Removed aerial work, SHEET 8: Removed aerial work & this sheet from package since work was removed
Total Completed Inspections - 3
Date Description Inspector Results Comments
02/15/2024 TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting Passed
05/21/2024 TRSP - ROW - Paving - Subgrade/removal/placement Passed
05/21/2024 TRSP - ROW - Final/Close-Out Passed

Documents

File Name Document Type  
P.090269_CAD REV2_03082024_V1.PDF DOCUMENTS VIEW
P.090269_TUCSON RESPONSE LETTER_V1.PDF DOCUMENTS VIEW
P.090269_TCP REV2_03082024_V1.PDF DOCUMENTS VIEW
COT - TR - ROW PERMIT.PDF DOCUMENTS VIEW
COT - TR - ROW PERMIT.PDF DOCUMENTS VIEW
P.090269 - CITY OF TUCSON TCP REV3 - 02-23-2024_V1.PDF DOCUMENTS VIEW
P.090269 - CITY OF TUCSON PLANS REV3 - 02-23-2024_V1.PDF DOCUMENTS VIEW
P.090269_TUCSON RESPONSE LETTER_V1.PDF DOCUMENTS VIEW
COT - TR - ROW PERMIT.PDF DOCUMENTS VIEW
P.090269 - CITY OF TUCSON PLANS - 12-20-2023 REV1_V2.PDF DOCUMENTS VIEW
P.090269 - CITY OF TUCSON TCP - 12-28-2023 REV2_V1.PDF DOCUMENTS VIEW
P.090269 - CITY OF TUCSON TCP - 10-30-2023_V1.PDF DOCUMENTS VIEW