Permit: TR-UTL-1023-02825
Permit Details
Apply Date:
10/30/2023
Applicant:
ANGEL MORALES
Description:
P.090269 (KAHNA) - BORE 2,383' & TRENCH 7' TO PLACE CTL CONDUIT & FIBER. PLACE (3) CABINET/HANDHOLE/PEDESTALS 3/12/2024 Revision: Traffic Control plans for TR-UTL-1023-02825 / CenturyLink Job # P.090269. Bore has been relocated and some aerial work has been removed; specifics SHEET 5: Bore location and length changed to North of E 26th St and on the East of S Craycroft Rd, SHEET 7: Removed aerial work, SHEET 8: Removed aerial work & this sheet from package since work was removed
Permit Reviews
Permit Number - TR-UTL-1023-02825
Permit Status: Issued
Permit Description: P.090269 (KAHNA) - BORE 2,383' & TRENCH 7' TO PLACE CTL CONDUIT & FIBER. PLACE (3) CABINET/HANDHOLE/PEDESTALS
3/12/2024 Revision: Traffic Control plans for TR-UTL-1023-02825 / CenturyLink Job # P.090269. Bore has been relocated and some aerial work has been removed; specifics SHEET 5: Bore location and length changed to North of E 26th St and on the East of S Craycroft Rd, SHEET 7: Removed aerial work, SHEET 8: Removed aerial work & this sheet from package since work was removed
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/23/2024 | RIGHT-OF-WAY REVIEW v.1 | 02/27/2024 | APPROVED |
10/30/2023 | RIGHT-OF-WAY REVIEW v.1 | 11/08/2023 | REQUIRES RESUBMIT |
03/11/2024 | RIGHT-OF-WAY REVIEW v.1 | 03/13/2024 | APPROVED |
12/28/2023 | RIGHT-OF-WAY REVIEW v.3 | 01/02/2024 | APPROVED |
12/20/2023 | RIGHT-OF-WAY REVIEW v.2 | 12/21/2023 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TR-UTL-1023-02825
Permit Status: Issued
Permit Description: P.090269 (KAHNA) - BORE 2,383' & TRENCH 7' TO PLACE CTL CONDUIT & FIBER. PLACE (3) CABINET/HANDHOLE/PEDESTALS
3/12/2024 Revision: Traffic Control plans for TR-UTL-1023-02825 / CenturyLink Job # P.090269. Bore has been relocated and some aerial work has been removed; specifics SHEET 5: Bore location and length changed to North of E 26th St and on the East of S Craycroft Rd, SHEET 7: Removed aerial work, SHEET 8: Removed aerial work & this sheet from package since work was removed
Total Outstanding Activity Conditions - 2
Date | Name |
---|---|
10/31/2023 | ** PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. ** PAVEMENT PATCH TYPE SHALL BE IN CONFORMANCE TO THE CURRENT EDITION OF THE CITY OF TUCSON PUBLIC UTILITY ADMINISTRATIVE MANUAL. **SIDEWALK CLOSED AHEAD SIGNS SHALL BE PLACED AT THE NEAREST ADA ACCESS RAMPS PER MUTCD CHAPTER 6D. |
10/31/2023 | Traffic control set-up approved between 9AM - 3:30PM |
Outstanding Inspections
Permit Status: Issued
Permit Number: TR-UTL-1023-02825
Permite Description: P.090269 (KAHNA) - BORE 2,383' & TRENCH 7' TO PLACE CTL CONDUIT & FIBER. PLACE (3) CABINET/HANDHOLE/PEDESTALS
3/12/2024 Revision: Traffic Control plans for TR-UTL-1023-02825 / CenturyLink Job # P.090269. Bore has been relocated and some aerial work has been removed; specifics SHEET 5: Bore location and length changed to North of E 26th St and on the East of S Craycroft Rd, SHEET 7: Removed aerial work, SHEET 8: Removed aerial work & this sheet from package since work was removed
Total Outstanding Inspections - 1
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
02/20/2024 | TRSP - ROW - Backfill - Placement/Compaction | N/A | Re-inspection required |
Completed Inspections
Permit Status: Issued
Permit Number: TR-UTL-1023-02825
Permit Description: P.090269 (KAHNA) - BORE 2,383' & TRENCH 7' TO PLACE CTL CONDUIT & FIBER. PLACE (3) CABINET/HANDHOLE/PEDESTALS
3/12/2024 Revision: Traffic Control plans for TR-UTL-1023-02825 / CenturyLink Job # P.090269. Bore has been relocated and some aerial work has been removed; specifics SHEET 5: Bore location and length changed to North of E 26th St and on the East of S Craycroft Rd, SHEET 7: Removed aerial work, SHEET 8: Removed aerial work & this sheet from package since work was removed
Total Completed Inspections - 3
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
02/15/2024 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | ||
05/21/2024 | TRSP - ROW - Paving - Subgrade/removal/placement | Passed | ||
05/21/2024 | TRSP - ROW - Final/Close-Out | Passed |