Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Complete
Type:
Right-of-Way (ROW) - Utility
Apply Date:
10/31/2022
Applicant:
Bob Roggenthen
Description:
SWG will be relocating distribution facilities that are in conflict with the city's roadway improvement plans. Additionally, SWG will be replacing all the vintage plastic within the project scope.

Permit Reviews

Permit Number - TR-UTL-1022-00130
Permit Status: Complete
Permit Description: SWG will be relocating distribution facilities that are in conflict with the city's roadway improvement plans. Additionally, SWG will be replacing all the vintage plastic within the project scope.
Start Date Submittal Complete Date Status  
11/15/2022 RIGHT-OF-WAY REVIEW v.1 11/15/2022 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TR-UTL-1022-00130
Permit Status: Complete
Permit Description: SWG will be relocating distribution facilities that are in conflict with the city's roadway improvement plans. Additionally, SWG will be replacing all the vintage plastic within the project scope.
Total Outstanding Activity Conditions - 2
Date Name
11/15/2022 Traffic control set-up approved between 9AM - 3:30PM
11/22/2022 The extended traffic control set-up times were approved per traffic control plan.

Outstanding Inspections

Permit Status: Complete
Permit Number: TR-UTL-1022-00130
Permite Description: SWG will be relocating distribution facilities that are in conflict with the city's roadway improvement plans. Additionally, SWG will be replacing all the vintage plastic within the project scope.
Total Outstanding Inspections - 1
Last Inspection Date Description Inspector Results Comments
01/09/2023 TRSP - ROW - SITE INSPECTION N/A Complete (Recurring)

Completed Inspections

Permit Status: Complete
Permit Number: TR-UTL-1022-00130
Permit Description: SWG will be relocating distribution facilities that are in conflict with the city's roadway improvement plans. Additionally, SWG will be replacing all the vintage plastic within the project scope.
Total Completed Inspections - 4
Date Description Inspector Results Comments
01/17/2023 TRSP - ROW - Recurring Passed
12/22/2022 TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting Passed no one is on site due to holiday work schedule. the traffic control is good.
03/29/2023 TRSP - ROW - SITE INSPECTION Passed
04/21/2023 TRSP - ROW - Final/Close-Out Passed

Documents

File Name Document Type  
TEMPORARY NOISE EXEMPTION.PDF DOCUMENTS VIEW
TCP TR-UTL-1022-00130.PDF DOCUMENTS VIEW
TCP TR-UTL-1022-00130_V3_APPROVED.PDF DOCUMENTS VIEW
TRAFFIC CONTROL PLAN_REV2_APPROVED.PDF DOCUMENTS VIEW
36_4465846_V1.PDF DOCUMENTS VIEW
COT_ROW_APPLICATION_REV112018.PDF DOCUMENTS VIEW
TRAFFIC CONTROL PLAN_REV1_APPROVED.PDF DOCUMENTS VIEW