Permit Details

Status:
Fees Due
Type:
Right-of-Way (ROW) - Utility
Address:
3755 S BELMAR AV
Address NEW:
3755 S BELMAR AV
Apply Date:
09/25/2026
Applicant:
Brittany West
Description:
Continue from phase 6. Hang 3,565ft of new strand and 144ct fiber.install a new riser and bore along proposed path for 500' at a depth of 36". install a new riser on the utility pole in the jack in the box parking lot.hang 890ft of new strand and new 144ct fiber ending at self sustained pole for I-10 crossing.

Permit Reviews

Permit Number - TR-UTL-0926-01658
Permit Status: Fees due
Permit Description: Continue from phase 6. Hang 3,565ft of new strand and 144ct fiber.install a new riser and bore along proposed path for 500' at a depth of 36". install a new riser on the utility pole in the jack in the box parking lot.hang 890ft of new strand and new 144ct fiber ending at self sustained pole for I-10 crossing.
Start Date Submittal Complete Date Status  
10/22/2026 RIGHT-OF-WAY REVIEW v.2 10/25/2026 REQUIRES RESUBMIT Review Details
10/26/2026 RIGHT-OF-WAY REVIEW v.3 10/28/2026 APPROVED Review Details
09/25/2026 RIGHT-OF-WAY REVIEW v.1 10/07/2026 REQUIRES RESUBMIT Review Details

Outstanding Activity Conditions

Permit Number - TR-UTL-0926-01658
Permit Status: Fees due
Permit Description: Continue from phase 6. Hang 3,565ft of new strand and 144ct fiber.install a new riser and bore along proposed path for 500' at a depth of 36". install a new riser on the utility pole in the jack in the box parking lot.hang 890ft of new strand and new 144ct fiber ending at self sustained pole for I-10 crossing.
Total Outstanding Activity Conditions - 11
Date Name
10/01/2026 Bus stop in the area, contact Joe Garcia, Sun Tran Dispatch, at 520-576-8726 at least 48-business hours prior to start of work for coordination
10/01/2026 Traffic control set-up approved between 9AM - 3:30PM
10/01/2026 A NOTICE OF TEMPORARY HOLIDAY RESTRICTION applies to this permit and will be in effect from Thanksgiving Day to January 02. Due to the increasing traffic volume on many of the City’s roads, it is necessary to restrict lane closures on certain roads during the holiday season.
10/28/2026 Your project work requires that you contact the Tucson Unified School District to alert them and coordinate work as needed in school zones.
10/28/2026 El Tour De Tucson Event Restriction Nov 21st, 2026
10/28/2026 Bike Lane Access and Accommodation 1) Posted Speeds 30 Mph or Less – Less than 14 lane - Use of the R4-11 alone is acceptable and preferred over Share The Road sign - 2) Posted Speeds 30 Mph or less – greater than 14 lane - Use of Share The Road sign is preferred 3) Posted Speeds 30 Mph or More – Any Lane Size - Provide a reasonable alternative for cyclists, such as a paved path, space behind barricades, or bike detour. Acceptable to direct cyclists to the sidewalk when properly signed depending on conditions 4) Bike lane to be maintained within Traffic Control closure and Share may Pedestrian detour path with proper R9-6 Sign.
10/28/2026 Lane closures shall only be permitted during active work operations. At the end of each workday, the contractor shall remove all traffic control devices and reopen the roadway, bike lanes, and sidewalks to normal operation. Twenty-four (24) hour lane closures are not permitted unless specifically approved by the City. Traffic Control Devices shall not be stored in the bike lane or sidewalk
10/28/2026 Pedestrian Access & Sidewalk PEDESTRIAN ACCESS MUST BE PROVIDED AND MAINTIANED PER MUTCD CHAPTER 6D. FIELD ADJUSTMENTS MAY BE REQUIRED. REPLACE/REPAIR SIDEWALK PANELS PER PAG STANDARD DETAIL 200\206 . PEDESTRIAN DETOUR ROUTE ON SAME SIDE OF RIGHT OF WAY TO BE PROVIDED. PER CITY CODE AND POLICY. Refer to MUTCD Chapter 6 Figure 6P-28, and 6K figure 6K-2. Refer to COT Utility manual Page 41 - 42 Refer to COT 2015 Addition to the MUTCD section 14
10/28/2026 Pre-Activity Meeting w/Inspections Pre- activity/construction meeting with City inspectors to be held 72 hours in advance of work start. Please request Inspections in your permit portal on TDC Online. PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING
10/28/2026 Rolling shadow traffic control closures not to exceed 2 hrs in a single location, with onsite flaggers for right of way with less than 2 travel lanes in each direction. Closures that exceed 2 hrs will require full traffic control setups based on road configuration.
10/28/2026 Traffic Control set-up approved between 7AM - 5PM

Documents

File Name Document Type  
DESIGN PLAN-JB0002329112_PERMIT MAP_PHASE 7-A1_V1.PDF DOCUMENTS VIEW
ENGINNERING DRAFT_V1.PDF DOCUMENTS VIEW
TCP REVISED 1_V1.PDF DOCUMENTS VIEW
TCP REVISED 2_V1.PDF DOCUMENTS VIEW
TCP REVISED 3_V1.PDF DOCUMENTS VIEW