Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
Inspections
Type:
Right-of-Way (ROW) - Utility
Address NEW:
4205 S QUEEN PALM DR
Apply Date:
09/15/2026
Applicant:
Description:
We are going to be potholing for utilities in 2 locations: 1. Intersection of S Heather Place/S Queen Palm Dr 2. Intersection of E Dogwood St/S White Pine Dr

Permit Reviews

Permit Number - TR-UTL-0926-01587
Permit Status: Inspections
Permit Description: We are going to be potholing for utilities in 2 locations: 1. Intersection of S Heather Place/S Queen Palm Dr 2. Intersection of E Dogwood St/S White Pine Dr
Start Date Submittal Complete Date Status  
09/22/2026 RIGHT-OF-WAY REVIEW v.2 10/01/2026 APPROVED Review Details
09/16/2026 RIGHT-OF-WAY REVIEW v.1 09/22/2026 REQUIRES RESUBMIT Review Details

Outstanding Activity Conditions

Permit Number - TR-UTL-0926-01587
Permit Status: Inspections
Permit Description: We are going to be potholing for utilities in 2 locations: 1. Intersection of S Heather Place/S Queen Palm Dr 2. Intersection of E Dogwood St/S White Pine Dr
Total Outstanding Activity Conditions - 4
Date Name
09/22/2026 Notify in writing at least 5 working days before work begins, any businesses, residences and public transit routes affected by your temporary traffic control. PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING.
09/22/2026 PAVEMENT MORATORIUM
09/22/2026 Pre- activity/construction meeting with City inspectors to be held 72 hours in advance of work start. Please request Inspections in your permit portal on TDC Online.
09/22/2026 Traffic Control set-up approved between 7AM - 5PM

Completed Inspections

Permit Status: Inspections
Permit Number: TR-UTL-0926-01587
Permit Description: We are going to be potholing for utilities in 2 locations: 1. Intersection of S Heather Place/S Queen Palm Dr 2. Intersection of E Dogwood St/S White Pine Dr
Total Completed Inspections - 2
Date Description Inspector Results Comments
10/12/2026 TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting Passed onsite meeting with Desert Earth. Potholes will be in moratorium pavement and follow SD 219. Flyers still needed for neighborhood notification. Mobilization will be scheduled after flyers. Shared Jeremy G’s contact info for future inspections.
10/27/2026 TRSP - ROW - Barricade - Setup/Routine Passed Work is complete and traffic control has been removed.

Documents

File Name Document Type  
COT - TR - ROW PERMIT (SSRS).PDF DOCUMENTS VIEW
BOTH LOCATIONS-2026-09-22_V1.PDF DOCUMENTS VIEW
TCP BOTH LOCATIONS_V1.PDF DOCUMENTS VIEW