Permit: TR-UTL-0926-01563
Permit Details
Status:
Inspections
Type:
Right-of-Way (ROW) - Utility
Address:
1855 N 6TH AV
Address NEW:
1855 N 6TH AV
Apply Date:
09/11/2026
Applicant:
Brittany West
Description:
Tie point will be existing aerial splice case. Place 815' of new strand over 7 spans. Lash 815' of 48ct fiber. Place new vault, vault will be located behind curb with no impact to any travel lane, bike lane or pavement. Bore 450' of 2" conduit at a depth of 3'. Approx 100ft of the 450' will be on E Ventura St. Bore running line will be located behind curb with no impact to sidewalk, travel lanes, bike lanes or pavement. 350' of the 450' will be in the alley with no impact to sidewalk, travel lanes, bike lanes. Run 450' of 48 ct fiber. Place new vault, vault will be located behind curb with no impact to any travel lane, bike lane or pavement. Place new vault, vault will be located behind curb with no impact to any travel lane, bike lane or pavement. Bore 35' of 2" conduit at a depth of 3', bore will be crossing the alley into private property with no impact to sidewalk, travel lanes, bike lanes. Run 35' of 48ct fiber.
Permit Reviews
Permit Number - TR-UTL-0926-01563
Permit Status: Inspections
Permit Description: Tie point will be existing aerial splice case. Place 815' of new strand over 7 spans. Lash 815' of 48ct fiber. Place new vault, vault will be located behind curb with no impact to any travel lane, bike lane or pavement. Bore 450' of 2" conduit at a depth of 3'. Approx 100ft of the 450' will be on E Ventura St. Bore running line will be located behind curb with no impact to sidewalk, travel lanes, bike lanes or pavement. 350' of the 450' will be in the alley with no impact to sidewalk, travel lanes, bike lanes. Run 450' of 48 ct fiber. Place new vault, vault will be located behind curb with no impact to any travel lane, bike lane or pavement. Place new vault, vault will be located behind curb with no impact to any travel lane, bike lane or pavement. Bore 35' of 2" conduit at a depth of 3', bore will be crossing the alley into private property with no impact to sidewalk, travel lanes, bike lanes. Run 35' of 48ct fiber.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 09/14/2026 | RIGHT-OF-WAY REVIEW v.1 | 10/09/2026 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-UTL-0926-01563
Permit Status: Inspections
Permit Description: Tie point will be existing aerial splice case. Place 815' of new strand over 7 spans. Lash 815' of 48ct fiber. Place new vault, vault will be located behind curb with no impact to any travel lane, bike lane or pavement. Bore 450' of 2" conduit at a depth of 3'. Approx 100ft of the 450' will be on E Ventura St. Bore running line will be located behind curb with no impact to sidewalk, travel lanes, bike lanes or pavement. 350' of the 450' will be in the alley with no impact to sidewalk, travel lanes, bike lanes. Run 450' of 48 ct fiber. Place new vault, vault will be located behind curb with no impact to any travel lane, bike lane or pavement. Place new vault, vault will be located behind curb with no impact to any travel lane, bike lane or pavement. Bore 35' of 2" conduit at a depth of 3', bore will be crossing the alley into private property with no impact to sidewalk, travel lanes, bike lanes. Run 35' of 48ct fiber.
Total Outstanding Activity Conditions - 8
| Date | Name |
|---|---|
| 09/17/2026 | Alley must be restored to existing or better condition. Alley surface must be graded and compacted to City Standards and Specifications for Public Improvements and existing drainage patterns must be restored and maintained. Any disturbed gravel must be replaced. |
| 09/17/2026 | Notify in writing at least 5 working days before work begins, any businesses, residences and public transit routes affected by your temporary traffic control. PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. |
| 09/17/2026 | Pre- activity/construction meeting with City inspectors to be held 72 hours in advance of work start. Please request Inspections in your permit portal on TDC Online. |
| 09/17/2026 | Traffic control set-up approved between 9AM - 3:30PM |
| 09/17/2026 | Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area. |
| 10/09/2026 | All excavations shall be secured for safety at the end of each shift. If pedestrian access cannot be maintained, a temporary protected pedestrian route shall be provided. All open trenches shall be protected by Type II barricades with Type A flashers and surrounded by a barrier fence. Trenches deeper than 4 feet shall be surrounded by chain-link fence. Excavations may need to be covered with steel plates or other approved materials at the end of each shift. |
| 10/09/2026 | The contractor shall not block driveways or restrict resident access without prior notification and shall coordinate directly with affected property owners as necessary. |
| 10/09/2026 | The contractor shall restore all disturbed pavement in accordance with the City of Tucson Standard Specifications for Public Improvements and applicable standard details. All pavement patches shall match the existing pavement section and surface condition. The contractor shall maintain temporary patches in a safe and drivable condition until permanent restoration is completed. Any settlement, cracking, or pavement failure within the patched area shall be repaired by the contractor at no cost to the City for the duration of the warranty period. |
Completed Inspections
Permit Status: Inspections
Permit Number: TR-UTL-0926-01563
Permit Description: Tie point will be existing aerial splice case. Place 815' of new strand over 7 spans. Lash 815' of 48ct fiber. Place new vault, vault will be located behind curb with no impact to any travel lane, bike lane or pavement. Bore 450' of 2" conduit at a depth of 3'. Approx 100ft of the 450' will be on E Ventura St. Bore running line will be located behind curb with no impact to sidewalk, travel lanes, bike lanes or pavement. 350' of the 450' will be in the alley with no impact to sidewalk, travel lanes, bike lanes. Run 450' of 48 ct fiber. Place new vault, vault will be located behind curb with no impact to any travel lane, bike lane or pavement. Place new vault, vault will be located behind curb with no impact to any travel lane, bike lane or pavement. Bore 35' of 2" conduit at a depth of 3', bore will be crossing the alley into private property with no impact to sidewalk, travel lanes, bike lanes. Run 35' of 48ct fiber.
Total Completed Inspections - 1
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/06/2026 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | Ariel and underground |