Permit: TR-UTL-0926-01517
Permit Details
Status:
Inspections
Type:
Right-of-Way (ROW) - Utility
Address:
5601 E 23RD ST
Address NEW:
5601 E 23RD ST
Apply Date:
09/03/2026
Applicant:
Arnulfo Quiroz
Description:
WO T159092. Crews to park in the City of Tucson ROW to replace (10) TEP poles, OH conductors, and OH attachments. Down guy anchors are to be replaced at (4) pole locations. Total Working days: 55 days.
Permit Reviews
Permit Number - TR-UTL-0926-01517
Permit Status: Inspections
Permit Description: WO T159092. Crews to park in the City of Tucson ROW to replace (10) TEP poles, OH conductors, and OH attachments. Down guy anchors are to be replaced at (4) pole locations. Total Working days: 55 days.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 10/05/2026 | RIGHT-OF-WAY REVIEW v.2 | 10/09/2026 | APPROVED |
| 09/03/2026 | RIGHT-OF-WAY REVIEW v.1 | 09/30/2026 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TR-UTL-0926-01517
Permit Status: Inspections
Permit Description: WO T159092. Crews to park in the City of Tucson ROW to replace (10) TEP poles, OH conductors, and OH attachments. Down guy anchors are to be replaced at (4) pole locations. Total Working days: 55 days.
Total Outstanding Activity Conditions - 5
| Date | Name |
|---|---|
| 09/08/2026 | Alley must be restored to existing or better condition. Alley surface must be graded and compacted to City Standards and Specifications for Public Improvements and existing drainage patterns must be restored and maintained. Any disturbed gravel must be replaced. |
| 09/08/2026 | Notify in writing at least 5 working days before work begins, any businesses, residences and public transit routes affected by your temporary traffic control. PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. |
| 09/08/2026 | Pre- activity/construction meeting with City inspectors to be held 72 hours in advance of work start. Please request Inspections in your permit portal on TDC Online. |
| 09/08/2026 | Traffic control set-up approved between 9AM - 3:30PM |
| 09/08/2026 | Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area. |
Completed Inspections
Permit Status: Inspections
Permit Number: TR-UTL-0926-01517
Permit Description: WO T159092. Crews to park in the City of Tucson ROW to replace (10) TEP poles, OH conductors, and OH attachments. Down guy anchors are to be replaced at (4) pole locations. Total Working days: 55 days.
Total Completed Inspections - 1
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/15/2026 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | I spoke with Rudy Villasenor over the phone and he relayed to me that would would still be 2 weeks out because he was still waiting on the ok from his company before bluestakes were even called. |