Permit: TR-UTL-0926-01507
Permit Details
Status:
Needs Resubmittal
Type:
Right-of-Way (ROW) - Utility
Address:
3900 N SUN TRAN BL
Address NEW:
3900 N SUN TRAN BL
Apply Date:
09/02/2026
Applicant:
Ilana Galluzzo
Description:
CONTINUATION OF PERMIT TR-UTL-0426-00731 TO COMPLETE PAVEMENT RESTORATION - ESTIMATING 10 MORE WORKING DAYS IN THE ROW BUT REQUESTING 60 DAYS FOR PERMIT TO ALLOW TIME FOR CONTRACTOR CITY OF TUCSON SUN TRAN NW CNG STATION HIGH PRESSURE GAS MAIN EXTENSION - Boring and trenching along Runway Dr and Sun Tran Blvd. Approx. 1404' of trenching/boring in dirt and approx. 1100 of trenching/boring in pavement.
Permit Reviews
Permit Number - TR-UTL-0926-01507
Permit Status: Needs resubmittal
Permit Description: CONTINUATION OF PERMIT TR-UTL-0426-00731 TO COMPLETE PAVEMENT RESTORATION - ESTIMATING 10 MORE WORKING DAYS IN THE ROW BUT REQUESTING 60 DAYS FOR PERMIT TO ALLOW TIME FOR CONTRACTOR
CITY OF TUCSON SUN TRAN NW CNG STATION HIGH PRESSURE GAS MAIN EXTENSION - Boring and trenching along Runway Dr and Sun Tran Blvd. Approx. 1404' of trenching/boring in dirt and approx. 1100 of trenching/boring in pavement.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 09/02/2026 | RIGHT-OF-WAY REVIEW v.1 | 09/09/2026 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TR-UTL-0926-01507
Permit Status: Needs resubmittal
Permit Description: CONTINUATION OF PERMIT TR-UTL-0426-00731 TO COMPLETE PAVEMENT RESTORATION - ESTIMATING 10 MORE WORKING DAYS IN THE ROW BUT REQUESTING 60 DAYS FOR PERMIT TO ALLOW TIME FOR CONTRACTOR
CITY OF TUCSON SUN TRAN NW CNG STATION HIGH PRESSURE GAS MAIN EXTENSION - Boring and trenching along Runway Dr and Sun Tran Blvd. Approx. 1404' of trenching/boring in dirt and approx. 1100 of trenching/boring in pavement.
Total Outstanding Activity Conditions - 4
| Date | Name |
|---|---|
| 09/08/2026 | Bus stop in the area, contact Joe Garcia, Sun Tran Dispatch, at 520-576-8726 at least 48-business hours prior to start of work for coordination |
| 09/08/2026 | **Pre-Activity Meeting w/Inspections **Pre- activity/construction meeting with City inspectors to be held 72 hours in advance of work start. Please request Inspections in your permit portal on TDC Online. ** PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. ** PAVEMENT PATCH TYPE SHALL BE IN CONFORMANCE TO THE CURRENT EDITION OF THE CITY OF TUCSON PUBLIC UTILITY ADMINISTRTIVE MANUAL **Pedestrian Access & Sidewalk PEDESTRIAN ACCESS MUST BE PROVIDED AND MAINTIANED PER MUTCD CHAPTER 6D. FIELD ADJUSTMENTS MAY BE REQUIRED. REPLACE/REPAIR SIDEWALK PANELS PER PAG STANDARD DETAIL 200\206 . PEDESTRIAN DETOUR ROUTE ON SAME SIDE OF RIGHT OF WAY TO BE PROVIDED. PER CITY CODE AND POLICY. Refer to MUTCD Chapter 6 Figure 6P-28, and 6K figure 6K-2. Refer to COT Utility manual Page 41 – 42 Refer to COT 2015 Addition to the MUTCD section 14 |
| 09/08/2026 | Traffic control set-up approved between 9AM - 3:30PM |
| 09/08/2026 | Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area. |