Permit: TR-UTL-0926-01502
Permit Details
Status:
Inspections
Type:
Right-of-Way (ROW) - Utility
Address:
719 W 41ST ST
Address NEW:
719 W 41ST ST
Apply Date:
09/02/2026
Applicant:
Adrien Pineda
Description:
ARIZONA PIPELINE WILL NEED TO EXCAVATE 1 45'X2' TRENCH IN DIRT/SIDEWALK ROW IN ORDER TO REPLACE GAS SERVICE , APPROX TOTAL IMPACT DAYS WILL BE 5 APPROX YARDAGE IS 15
Permit Reviews
Permit Number - TR-UTL-0926-01502
Permit Status: Inspections
Permit Description: ARIZONA PIPELINE WILL NEED TO EXCAVATE 1 45'X2' TRENCH IN DIRT/SIDEWALK ROW IN ORDER TO REPLACE GAS SERVICE , APPROX TOTAL IMPACT DAYS WILL BE 5 APPROX YARDAGE IS 15
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 09/02/2026 | RIGHT-OF-WAY REVIEW v.1 | 09/09/2026 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-UTL-0926-01502
Permit Status: Inspections
Permit Description: ARIZONA PIPELINE WILL NEED TO EXCAVATE 1 45'X2' TRENCH IN DIRT/SIDEWALK ROW IN ORDER TO REPLACE GAS SERVICE , APPROX TOTAL IMPACT DAYS WILL BE 5 APPROX YARDAGE IS 15
Total Outstanding Activity Conditions - 3
| Date | Name |
|---|---|
| 09/03/2026 | **Pre-Activity Meeting w/Inspections **Pre- activity/construction meeting with City inspectors to be held 72 hours in advance of work start. Please request Inspections in your permit portal on TDC Online. ** PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. ** PAVEMENT PATCH TYPE SHALL BE IN CONFORMANCE TO THE CURRENT EDITION OF THE CITY OF TUCSON PUBLIC UTILITY ADMINISTRTIVE MANUAL **Pedestrian Access & Sidewalk PEDESTRIAN ACCESS MUST BE PROVIDED AND MAINTIANED PER MUTCD CHAPTER 6D. FIELD ADJUSTMENTS MAY BE REQUIRED. REPLACE/REPAIR SIDEWALK PANELS PER PAG STANDARD DETAIL 200\206 . PEDESTRIAN DETOUR ROUTE ON SAME SIDE OF RIGHT OF WAY TO BE PROVIDED. PER CITY CODE AND POLICY. Refer to MUTCD Chapter 6 Figure 6P-28, and 6K figure 6K-2. Refer to COT Utility manual Page 41 – 42 Refer to COT 2015 Addition to the MUTCD section 14 |
| 09/03/2026 | PAVEMENT MORATORIUM: ANY NEW ASPHALT THAT IS DISTURBED WILL REQUIRE A 2” MILL AND OVERLAY FOR 25’ IN EACH DIRECTION FROM THE OUTSIDE OF THE CUT FOR ALL EFFECTED TRAVEL LANES. |
| 09/03/2026 | Traffic Control set-up approved between 7AM - 5PM |
Completed Inspections
Permit Status: Inspections
Permit Number: TR-UTL-0926-01502
Permit Description: ARIZONA PIPELINE WILL NEED TO EXCAVATE 1 45'X2' TRENCH IN DIRT/SIDEWALK ROW IN ORDER TO REPLACE GAS SERVICE , APPROX TOTAL IMPACT DAYS WILL BE 5 APPROX YARDAGE IS 15
Total Completed Inspections - 2
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/11/2026 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | ||
| 10/28/2026 | TRSP - ROW - Backfill - Placement/Compaction | Passed |