Permit Details

Status:
In Revision
Type:
Right-of-Way (ROW) - Utility
Apply Date:
09/01/2026
Applicant:
Brittany West
Description:
Hang 2,825ft of new strand and new 144ct fiber. hang 2,415ft of new strand and 144ct fiber. bore along proposed path for 435ft at a depth of 36 inches. we will set 2 new vaults on each side of mission rd.

Permit Reviews

Permit Number - TR-UTL-0926-01485
Permit Status: In revision
Permit Description: Hang 2,825ft of new strand and new 144ct fiber. hang 2,415ft of new strand and 144ct fiber. bore along proposed path for 435ft at a depth of 36 inches. we will set 2 new vaults on each side of mission rd.
Start Date Submittal Complete Date Status  
10/22/2026 RIGHT-OF-WAY REVIEW v.2 10/26/2026 APPROVED Review Details
10/28/2026 RIGHT-OF-WAY REVIEW REVISION v.1 N/A IN REVIEW Review Details
09/01/2026 RIGHT-OF-WAY REVIEW v.1 10/01/2026 REQUIRES RESUBMIT Review Details

Outstanding Activity Conditions

Permit Number - TR-UTL-0926-01485
Permit Status: In revision
Permit Description: Hang 2,825ft of new strand and new 144ct fiber. hang 2,415ft of new strand and 144ct fiber. bore along proposed path for 435ft at a depth of 36 inches. we will set 2 new vaults on each side of mission rd.
Total Outstanding Activity Conditions - 7
Date Name
09/04/2026 This project is located in an Archaeological Sensitivity Zone. An Archaeological Monitor hired by the permit applicant is required to be on-site during any digging, unless a waiver is issued. Monitoring reports are to be submitted to Historic Preservation Office at PDSDHistoric@tucsonaz.gov.
09/04/2026 Notify in writing at least 5 working days before work begins, any businesses, residences and public transit routes affected by your temporary traffic control. PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING.
09/04/2026 Pre- activity/construction meeting with City inspectors to be held 72 hours in advance of work start. Please request Inspections in your permit portal on TDC Online.
09/04/2026 Traffic control set-up approved between 9AM - 3:30PM
09/04/2026 Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area.
10/26/2026 Continuous ADA-compliant pedestrian access shall be maintained at all times. If a sidewalk is closed, an approved temporary pedestrian access route shall be provided in accordance with the Manual on Uniform Traffic Control Devices.
10/26/2026 Lane and street closures shall be permitted only during active work operations. At the end of each workday, the contractor shall remove all traffic control devices and reopen the roadway, bike lanes, and sidewalks to normal operation. Twenty-four-hour lane closures are not permitted unless specifically approved by the City. Traffic control devices shall not be stored in a bike lane or sidewalk.

Documents

File Name Document Type  
COT - TR - ROW PERMIT (SSRS).PDF DOCUMENTS VIEW
DESIGN PLAN-JB0002329112_PERMIT MAP_PHASE 2 PART 1-A1_V1.PDF DOCUMENTS VIEW
MASTEC CITY_V1.PDF DOCUMENTS VIEW
ENGINEERING DRAFT_V1.PDF DOCUMENTS VIEW