Permit: TR-UTL-0925-01644
Permit Details
Status:
Complete
Type:
Right-of-Way (ROW) - Utility
Address:
1810 S AMALIA AV
Address NEW:
1810 S AMALIA AV
Apply Date:
09/23/2025
Applicant:
Austin Eslick
Description:
T139757 - Replace (30) existing TEP/TELCO distribution poles, (3) downguys, OH conductors, OH attachments, and OH transformers in alleyways to meet current TEP standards per Memo 2024C002 - PUEBLO GARDENS. 12/23/2025 - Request for 90 Day Renewal as of 01/05/2026
Permit Reviews
Permit Number - TR-UTL-0925-01644
Permit Status: Complete
Permit Description: T139757 - Replace (30) existing TEP/TELCO distribution poles, (3) downguys, OH conductors, OH attachments, and OH transformers in alleyways to meet current TEP standards per Memo 2024C002 - PUEBLO GARDENS.
12/23/2025 - Request for 90 Day Renewal as of 01/05/2026
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 09/23/2025 | RIGHT-OF-WAY REVIEW v.1 | 10/01/2025 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-UTL-0925-01644
Permit Status: Complete
Permit Description: T139757 - Replace (30) existing TEP/TELCO distribution poles, (3) downguys, OH conductors, OH attachments, and OH transformers in alleyways to meet current TEP standards per Memo 2024C002 - PUEBLO GARDENS.
12/23/2025 - Request for 90 Day Renewal as of 01/05/2026
Total Outstanding Activity Conditions - 3
| Date | Name |
|---|---|
| 09/25/2025 | COT ROW |
| 09/25/2025 | PRE-CON/PAVEMENT/SIDEWALK |
| 09/25/2025 | Traffic Control set-up approved between 7AM - 5PM |
Completed Inspections
Permit Status: Complete
Permit Number: TR-UTL-0925-01644
Permit Description: T139757 - Replace (30) existing TEP/TELCO distribution poles, (3) downguys, OH conductors, OH attachments, and OH transformers in alleyways to meet current TEP standards per Memo 2024C002 - PUEBLO GARDENS.
12/23/2025 - Request for 90 Day Renewal as of 01/05/2026
Total Completed Inspections - 4
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/23/2025 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | ||
| 03/31/2026 | TRSP - ROW - Barricade - Setup/Routine | Passed | ||
| 03/31/2026 | TRSP - ROW - Barricade Takedown | Passed | ||
| 03/31/2026 | TRSP - ROW - Final | Passed |