Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: TR-UTL-0925-01592
Permit Details
Status:
Needs Resubmittal
Type:
Right-of-Way (ROW) - Utility
Address:
3102 E PRESIDIO RD
Address NEW:
3102 E PRESIDIO RD
Apply Date:
09/18/2025
Applicant:
Tucson Electric Power
Description:
T162024 - 3102 E Presidio Rd, TEP to replace 1 pole and anchor, install 1 new pedestal and install 1 new pole
Permit Reviews
Permit Number - TR-UTL-0925-01592
Permit Status: Needs resubmittal
Permit Description: T162024 - 3102 E Presidio Rd, TEP to replace 1 pole and anchor, install 1 new pedestal and install 1 new pole
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 09/18/2025 | RIGHT-OF-WAY REVIEW v.1 | 09/18/2025 | REQUIRES RESUBMIT |
| 09/30/2025 | RIGHT-OF-WAY REVIEW v.2 | 10/01/2025 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TR-UTL-0925-01592
Permit Status: Needs resubmittal
Permit Description: T162024 - 3102 E Presidio Rd, TEP to replace 1 pole and anchor, install 1 new pedestal and install 1 new pole
Total Outstanding Activity Conditions - 6
| Date | Name |
|---|---|
| 09/18/2025 | Traffic control set-up approved between 9AM - 3:30PM |
| 09/30/2025 | BUS STOP IN AREA, CONTACT SUN TRAN DISPTCH AT 520.206.8934 AT LEAST 48-BUSINESS HOURS PRIOR TO START OF WORK FOR COORDINATION. |
| 09/30/2025 | Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area. |
| 10/01/2025 | Pedestrian Access & Sidewalk PEDESTRIAN ACCESS MUST BE PROVIDED AND MAINTIANED PER MUTCD CHAPTER 6D. FIELD ADJUSTMENTS MAY BE REQUIRED. REPLACE/REPAIR SIDEWALK PANELS PER PAG STANDARD DETAIL 200\206 . PEDESTRIAN DETOUR ROUTE ON SAME SIDE OF RIGHT OF WAY TO BE PROVIDED IF NO MARKED ADA RAMPS AND CROSSING ACCESSABLE WITHIN 660' OF SIDEWALK CLOSURE. ACCESSABLE. Refer to MUTCD Chapter 6 Figure 6P-28, and 6K figure 6K-2. Refer to COT Utility manual Page 41 - 42 Refer to COT 2015 Addition to the MUTCD section 14 |
| 10/01/2025 | Pre-Activity Meeting Pre- activity meeting to be held 72 hrs in advance of work start with inspections.. PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. |
| 10/01/2025 | Private Property Driveways and private property shall NOT be utilized without the owner’s consent. It is the contractor’s responsibility to negotiate use of private property |