Permit: TR-UTL-0924-01834
Permit Details
Apply Date:
09/23/2024
Applicant:
Fernando Soto
Description:
Crews will be boring and trenching in pavement/dirt. Approximately 4,078' in dirt, and approx. 2,891' in pavement to relocate gas service. THIS PROJECT INVOLVES THE RELOCATION OF EXISTING GAS FACILITIES IN ORDER TO ALLEVIATE CONFLICTS ASSOCIATED WITH CITY OF TUCSON HOUGHTON ROAD RECONSTRUCTION PROJECT FROM IRVINGTON TO 22ND. 10/24/2024 - Revised traffic control set up approved for 24 hour set up.
Permit Reviews
Permit Number - TR-UTL-0924-01834
Permit Status: Inspections
Permit Description: Crews will be boring and trenching in pavement/dirt. Approximately 4,078' in dirt, and approx. 2,891' in pavement to relocate gas service.
THIS PROJECT INVOLVES THE RELOCATION OF EXISTING GAS FACILITIES IN ORDER TO ALLEVIATE CONFLICTS ASSOCIATED WITH CITY OF TUCSON HOUGHTON ROAD RECONSTRUCTION PROJECT FROM IRVINGTON TO 22ND.
10/24/2024 - Revised traffic control set up approved for 24 hour set up.
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
10/16/2024 | RIGHT-OF-WAY REVIEW REVISION v.1 | 10/24/2024 | APPROVED |
09/23/2024 | RIGHT-OF-WAY REVIEW v.1 | 10/04/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-UTL-0924-01834
Permit Status: Inspections
Permit Description: Crews will be boring and trenching in pavement/dirt. Approximately 4,078' in dirt, and approx. 2,891' in pavement to relocate gas service.
THIS PROJECT INVOLVES THE RELOCATION OF EXISTING GAS FACILITIES IN ORDER TO ALLEVIATE CONFLICTS ASSOCIATED WITH CITY OF TUCSON HOUGHTON ROAD RECONSTRUCTION PROJECT FROM IRVINGTON TO 22ND.
10/24/2024 - Revised traffic control set up approved for 24 hour set up.
Total Outstanding Activity Conditions - 3
Date | Name |
---|---|
09/23/2024 | PRE-CON/PAVEMENT/SIDEWALK |
09/23/2024 | Traffic control set-up approved between 9AM - 3:30PM |
10/25/2024 | Traffic/Mobility Control Plan (MCP) approved as submitted. |
Outstanding Inspections
Permit Status: Inspections
Permit Number: TR-UTL-0924-01834
Permite Description: Crews will be boring and trenching in pavement/dirt. Approximately 4,078' in dirt, and approx. 2,891' in pavement to relocate gas service.
THIS PROJECT INVOLVES THE RELOCATION OF EXISTING GAS FACILITIES IN ORDER TO ALLEVIATE CONFLICTS ASSOCIATED WITH CITY OF TUCSON HOUGHTON ROAD RECONSTRUCTION PROJECT FROM IRVINGTON TO 22ND.
10/24/2024 - Revised traffic control set up approved for 24 hour set up.
Total Outstanding Inspections - 1
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/19/2024 | TRSP - ROW - SITE INSPECTION | N/A | Complete (Recurring) | excavation on northbound shoulder began, traffic control in place for shoulder closure from Irvington to Keystone |
Completed Inspections
Permit Status: Inspections
Permit Number: TR-UTL-0924-01834
Permit Description: Crews will be boring and trenching in pavement/dirt. Approximately 4,078' in dirt, and approx. 2,891' in pavement to relocate gas service.
THIS PROJECT INVOLVES THE RELOCATION OF EXISTING GAS FACILITIES IN ORDER TO ALLEVIATE CONFLICTS ASSOCIATED WITH CITY OF TUCSON HOUGHTON ROAD RECONSTRUCTION PROJECT FROM IRVINGTON TO 22ND.
10/24/2024 - Revised traffic control set up approved for 24 hour set up.
Total Completed Inspections - 1
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/19/2024 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed |