Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: TR-UTL-0924-01735
Permit Details
Apply Date:
09/12/2024
Applicant:
Chelsey Bolinger
Description:
P.067173B (KAHNA) – BORE 5,024’ TO PLACE CTL CONDUIT & FIBER CABLE. PLACE (3) HANDHOLES & (22) PEDESTALS.
Permit Reviews
Permit Number - TR-UTL-0924-01735
Permit Status: Issued
Permit Description: P.067173B (KAHNA) – BORE 5,024’ TO PLACE CTL CONDUIT & FIBER CABLE. PLACE (3) HANDHOLES & (22) PEDESTALS.
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
09/13/2024 | RIGHT-OF-WAY REVIEW v.1 | 09/16/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-UTL-0924-01735
Permit Status: Issued
Permit Description: P.067173B (KAHNA) – BORE 5,024’ TO PLACE CTL CONDUIT & FIBER CABLE. PLACE (3) HANDHOLES & (22) PEDESTALS.
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
09/16/2024 | Traffic Control set-up approved between 7AM - 5PM |
Completed Inspections
Permit Status: Issued
Permit Number: TR-UTL-0924-01735
Permit Description: P.067173B (KAHNA) – BORE 5,024’ TO PLACE CTL CONDUIT & FIBER CABLE. PLACE (3) HANDHOLES & (22) PEDESTALS.
Total Completed Inspections - 3
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/14/2024 | TRSP - ROW - Barricade - Setup/Routine | Passed | Barricades and signage in place, openings wrapped in snow fencing | |
11/14/2024 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | met with drilling crew and Pauley on 10/21, per Mike Brevin route is approved to move to behind curb to reduce restoration impact to asphalt, redlines to reflect new locations | |
11/18/2024 | TRSP - ROW - Backfill - Placement/Compaction | Passed | all sections of Permit B backfilled and completed |