Permit: TR-UTL-0924-01680
Permit Details
Status:
Complete
Type:
Right-of-Way (ROW) - Utility
Address:
6249 S EUCLID AV
Address NEW:
6249 S EUCLID AV
Apply Date:
09/09/2024
Applicant:
Chelsey Bolinger
Description:
P.122873A (KAHNA) – BORE 1,677’ & TRENCH 94’ TO PLACE CTL CONDUIT & FIBER CABLE. PLACE (1) FSAI CABINET, (2) HANDHOLES & (1) PEDESTAL. OVERLASH 3,235’ OF AERIAL FIBER CABLE.
Permit Reviews
Permit Number - TR-UTL-0924-01680
Permit Status: Complete
Permit Description: P.122873A (KAHNA) – BORE 1,677’ & TRENCH 94’ TO PLACE CTL CONDUIT & FIBER CABLE. PLACE (1) FSAI CABINET, (2) HANDHOLES & (1) PEDESTAL. OVERLASH 3,235’ OF AERIAL FIBER CABLE.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 09/09/2024 | RIGHT-OF-WAY REVIEW v.1 | 09/11/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-UTL-0924-01680
Permit Status: Complete
Permit Description: P.122873A (KAHNA) – BORE 1,677’ & TRENCH 94’ TO PLACE CTL CONDUIT & FIBER CABLE. PLACE (1) FSAI CABINET, (2) HANDHOLES & (1) PEDESTAL. OVERLASH 3,235’ OF AERIAL FIBER CABLE.
Total Outstanding Activity Conditions - 3
| Date | Name |
|---|---|
| 09/10/2024 | Alley must be restored to existing or better condition. Alley surface must be graded and compacted to City Standards and Specifications for Public Improvements and existing drainage patterns must be restored and maintained. Any disturbed gravel must be replaced. |
| 09/10/2024 | Traffic control set-up approved between 9AM - 3:30PM |
| 09/10/2024 | Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area. |
Completed Inspections
Permit Status: Complete
Permit Number: TR-UTL-0924-01680
Permit Description: P.122873A (KAHNA) – BORE 1,677’ & TRENCH 94’ TO PLACE CTL CONDUIT & FIBER CABLE. PLACE (1) FSAI CABINET, (2) HANDHOLES & (1) PEDESTAL. OVERLASH 3,235’ OF AERIAL FIBER CABLE.
Total Completed Inspections - 6
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/23/2024 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | ||
| 03/26/2025 | TRSP - ROW - Barricade - Setup/Routine | Passed | ||
| 03/26/2025 | TRSP - ROW - Barricade Takedown | Passed | ||
| 03/26/2025 | TRSP - ROW - Backfill - Placement/Compaction | Passed | ||
| 03/26/2025 | TRSP - ROW - AERIAL INSTALLATION | Passed | ||
| 03/26/2025 | TRSP - ROW - Final | Passed |