Permit Details

Status:
Complete
Type:
Right-of-Way (ROW) - Utility
Address NEW:
426 E MICHIGAN DR
Apply Date:
09/06/2024
Applicant:
Ilana Galluzzo
Description:
3' x 6' BELL HOLE IN DIRT WITH AN APPROX. 2' x 50' TRENCH IN ASPHALT/CONCRETE/DIRT CROSSING E MICHIGAN DRIVE TO INSTALL NEW GAS SERVICE

Permit Reviews

Permit Number - TR-UTL-0924-01668
Permit Status: Complete
Permit Description: 3' x 6' BELL HOLE IN DIRT WITH AN APPROX. 2' x 50' TRENCH IN ASPHALT/CONCRETE/DIRT CROSSING E MICHIGAN DRIVE TO INSTALL NEW GAS SERVICE
Start Date Submittal Complete Date Status  
09/06/2024 RIGHT-OF-WAY REVIEW v.1 09/09/2024 REQUIRES RESUBMIT Review Details
09/12/2024 RIGHT-OF-WAY REVIEW v.2 09/13/2024 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TR-UTL-0924-01668
Permit Status: Complete
Permit Description: 3' x 6' BELL HOLE IN DIRT WITH AN APPROX. 2' x 50' TRENCH IN ASPHALT/CONCRETE/DIRT CROSSING E MICHIGAN DRIVE TO INSTALL NEW GAS SERVICE
Total Outstanding Activity Conditions - 3
Date Name
09/06/2024 PRE-CON/PAVEMENT/SIDEWALK
09/06/2024 Traffic control set-up approved between 9AM - 3:30PM
09/09/2024 Active UPRR line with in proximity of Flagman station (70') . Notify UPRR Dispatch of Work, prior to Start of Work @ 1-888-UPRRCOP (877-7267).. Maintain Rail Crossing Safety during Flagging Activity.

Completed Inspections

Permit Status: Complete
Permit Number: TR-UTL-0924-01668
Permit Description: 3' x 6' BELL HOLE IN DIRT WITH AN APPROX. 2' x 50' TRENCH IN ASPHALT/CONCRETE/DIRT CROSSING E MICHIGAN DRIVE TO INSTALL NEW GAS SERVICE
Total Completed Inspections - 4
Date Description Inspector Results Comments
06/30/2026 TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting Passed
06/30/2026 TRSP - ROW - Backfill - Placement/Compaction Passed
06/30/2026 TRSP - ROW - Final Passed
06/30/2026 TRSP - ROW - Concrete - Subgrade/Forms (Pre-Pour) Passed