Permit: TR-UTL-0924-01652
Permit Details
Status:
Complete
Type:
Right-of-Way (ROW) - Utility
Address:
6223 S PALO VERDE RD
Address NEW:
6223 S PALO VERDE RD
Apply Date:
09/02/2024
Applicant:
Chelsey Bolinger
Description:
P.122865S (KAHNA) – TRENCH 10’ TO PLACE CTL CONDUIT AND FIBER CABLE. PLACE (1) HANDHOLE.
Permit Reviews
Permit Number - TR-UTL-0924-01652
Permit Status: Complete
Permit Description: P.122865S (KAHNA) – TRENCH 10’ TO PLACE CTL CONDUIT AND FIBER CABLE. PLACE (1) HANDHOLE.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 09/03/2024 | RIGHT-OF-WAY REVIEW v.1 | 09/03/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-UTL-0924-01652
Permit Status: Complete
Permit Description: P.122865S (KAHNA) – TRENCH 10’ TO PLACE CTL CONDUIT AND FIBER CABLE. PLACE (1) HANDHOLE.
Total Outstanding Activity Conditions - 2
| Date | Name |
|---|---|
| 09/03/2024 | ** PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. ** PAVEMENT PATCH TYPE SHALL BE IN CONFORMANCE TO THE CURRENT EDITION OF THE CITY OF TUCSON PUBLIC UTILITY ADMINISTRTIVE MANUAL **SIDEWALK CLOSED AHEAD SIGNS SHALL BE PLACED AT THE NEAREST ADA ACCESS RAMPS PER MUTCD CHAPTER 6D. |
| 09/03/2024 | Traffic Control set-up approved between 7AM - 5PM |
Outstanding Inspections
Permit Status: Complete
Permit Number: TR-UTL-0924-01652
Permite Description: P.122865S (KAHNA) – TRENCH 10’ TO PLACE CTL CONDUIT AND FIBER CABLE. PLACE (1) HANDHOLE.
Total Outstanding Inspections - 2
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/17/2024 | TRSP - ROW - Barricade - Setup/Routine | N/A | Not Ready | Awaiting permit extension |
| 12/17/2024 | TRSP - ROW - Final | N/A | Not Ready | Awaiting permit extension |
Completed Inspections
Permit Status: Complete
Permit Number: TR-UTL-0924-01652
Permit Description: P.122865S (KAHNA) – TRENCH 10’ TO PLACE CTL CONDUIT AND FIBER CABLE. PLACE (1) HANDHOLE.
Total Completed Inspections - 3
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/17/2024 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | Phone call with Robert, request for extension past 12/19 will be needed. Robert will keep me up-to-date on new permit extension. | |
| 04/09/2025 | TRSP - ROW - Barricade - Setup/Routine | Passed | Work is complete | |
| 04/09/2025 | TRSP - ROW - Final | Passed | Work is complete |