Permit: TR-UTL-0826-01415
Permit Details
Status:
Needs Resubmittal
Type:
Right-of-Way (ROW) - Utility
Address:
9672 E BANBRIDGE ST
Address NEW:
9672 E BANBRIDGE ST
Apply Date:
08/21/2026
Applicant:
ANGEL MORALES
Description:
P.361386A Overbuild: Bore 3905' and trench 152' to place conduit and fiber cable Place 44 pedestals/cabinets/vaults
Permit Reviews
Permit Number - TR-UTL-0826-01415
Permit Status: Needs resubmittal
Permit Description: P.361386A Overbuild:
Bore 3905' and trench 152' to place conduit and fiber cable
Place 44 pedestals/cabinets/vaults
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/21/2026 | RIGHT-OF-WAY REVIEW v.1 | 09/09/2026 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TR-UTL-0826-01415
Permit Status: Needs resubmittal
Permit Description: P.361386A Overbuild:
Bore 3905' and trench 152' to place conduit and fiber cable
Place 44 pedestals/cabinets/vaults
Total Outstanding Activity Conditions - 9
| Date | Name |
|---|---|
| 08/25/2026 | Alley must be restored to existing or better condition. Alley surface must be graded and compacted to City Standards and Specifications for Public Improvement and existing drainage patterns must be restored and maintained. Any disturbed gravel must be replaced. |
| 08/25/2026 | Traffic control set-up approved between 9AM - 3:30PM |
| 08/25/2026 | Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area. |
| 08/25/2026 | Pre- activity/construction meeting with City inspectors to be held 72 hours in advance of work start. Please request Inspections in your permit portal on TDC Online. |
| 08/25/2026 | PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. |
| 09/09/2026 | All excavations shall be secured for safety at the end of each shift. If pedestrian access cannot be maintained, a temporary protected pedestrian route shall be provided. All open trenches shall be protected by Type II barricades with Type A flashers and surrounded by a barrier fence. Trenches deeper than 4 feet shall be surrounded by chain-link fence. Excavations may need to be covered with steel plates or other approved materials at the end of each shift. |
| 09/09/2026 | Lane and street closures shall be permitted only during active work operations. At the end of each workday, the contractor shall remove all traffic control devices and reopen the roadway, bike lanes, and sidewalks to normal operation. Twenty-four-hour lane closures are not permitted unless specifically approved by the City. Traffic control devices shall not be stored in a bike lane or sidewalk. |
| 09/09/2026 | The contractor shall protect all existing landscaping and irrigation within the work area. Any landscaping disturbed or damaged by construction activities shall be restored to equal or better condition, including replacement of plant material, decomposed granite or groundcover, irrigation components, and hardscape, as applicable. All repairs shall be completed to the satisfaction of the City Inspector at no cost to the City. |
| 09/09/2026 | The contractor shall restore all disturbed pavement in accordance with the City of Tucson Standard Specifications for Public Improvements and applicable standard details. All pavement patches shall match the existing pavement section and surface condition. The contractor shall maintain temporary patches in a safe and drivable condition until permanent restoration is completed. Any settlement, cracking, or pavement failure within the patched area shall be repaired by the contractor at no cost to the City for the duration of the warranty period. |