Permit Details

Status:
Inspections
Type:
Right-of-Way (ROW) - Utility
Apply Date:
08/03/2026
Applicant:
Aidan Willis
Description:
Zayo Contractor ADB Companies to install conduit/fiber via Directional Bore and open trench for an estimated 5,283 LF. Zayo Handholes to be installed every 2,000 LF for future access and maintenance.

Permit Reviews

Permit Number - TR-UTL-0826-01284
Permit Status: Inspections
Permit Description: Zayo Contractor ADB Companies to install conduit/fiber via Directional Bore and open trench for an estimated 5,283 LF. Zayo Handholes to be installed every 2,000 LF for future access and maintenance.
Start Date Submittal Complete Date Status  
08/03/2026 RIGHT-OF-WAY REVIEW v.1 08/05/2026 REQUIRES RESUBMIT Review Details
09/03/2026 RIGHT-OF-WAY REVIEW v.3 09/09/2026 APPROVED Review Details
08/20/2026 RIGHT-OF-WAY REVIEW v.2 08/20/2026 REQUIRES RESUBMIT Review Details

Outstanding Activity Conditions

Permit Number - TR-UTL-0826-01284
Permit Status: Inspections
Permit Description: Zayo Contractor ADB Companies to install conduit/fiber via Directional Bore and open trench for an estimated 5,283 LF. Zayo Handholes to be installed every 2,000 LF for future access and maintenance.
Total Outstanding Activity Conditions - 8
Date Name
08/03/2026 Bus stop in the area, contact Joe Garcia, Sun Tran Dispatch, at 520-576-8726 at least 48-business hours prior to start of work for coordination.
08/03/2026 PAVEMENT MORATORIUM: ANY NEW ASPHALT THAT IS DISTURBED WILL REQUIRE A 2” MILL AND OVERLAY FOR 25’ IN EACH DIRECTION FROM THE OUTSIDE OF THE CUT FOR ALL EFFECTED TRAVEL LANES.
08/03/2026 Traffic control set-up approved between 9AM - 3:30PM
08/03/2026 Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area.
09/08/2026 Bike Lane Access and Accommodation 1) Posted Speeds 30 Mph or Less – Less than 14 lane - Use of the R4-11 alone is acceptable and preferred over Share The Road sign - 2) Posted Speeds 30 Mph or less – greater than 14 lane - Use of Share The Road sign is preferred 3) Posted Speeds 30 Mph or More – Any Lane Size - Provide a reasonable alternative for cyclists, such as a paved path, space behind barricades, or bike detour. Acceptable to direct cyclists to the sidewalk when properly signed depending on conditions 4) Bike lane to be maintained within Traffic Control closure and Share may Pedestrian detour path with proper R9-6 Sign.
09/08/2026 Noted 1-3 day set up= $0 Loss of Use fee. No Estimate provided at this time. Total Loss of Use to be determined by physical field inspection review at Permit Closeout"
09/08/2026 Pedestrian Access & Sidewalk PEDESTRIAN ACCESS MUST BE PROVIDED AND MAINTIANED PER MUTCD CHAPTER 6D. FIELD ADJUSTMENTS MAY BE REQUIRED. REPLACE/REPAIR SIDEWALK PANELS PER PAG STANDARD DETAIL 200\206 . PEDESTRIAN DETOUR ROUTE ON SAME SIDE OF RIGHT OF WAY TO BE PROVIDED. PER CITY CODE AND POLICY. Refer to MUTCD Chapter 6 Figure 6P-28, and 6K figure 6K-2. Refer to COT Utility manual Page 41 - 42 Refer to COT 2015 Addition to the MUTCD section 14
09/08/2026 Pre-Activity Meeting w/Inspections Pre- activity/construction meeting with City inspectors to be held 72 hours in advance of work start. Please request Inspections in your permit portal on TDC Online. PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING

Documents

File Name Document Type  
COT - TR - ROW PERMIT (SSRS).PDF DOCUMENTS VIEW
ADB - ZAYO - VBP-006717 PHOENIX AZ TO TUCSON AZ LH FIBER BUILD_TUCSON_(MILE-1)_V2.PDF DOCUMENTS VIEW
JUST RIGHT - 1800 N STONE AVE - STONE RIGHT LN CL WITH ADA WALL PLAN 3 - FIBER BUILD - VBP-006717_V3.PDF DOCUMENTS VIEW
JUST RIGHT - 251 W BLACKLIDGE DR - BLACKLIDGE FLAGGER STATION PLAN 2 - FIBER BUILD - VBP-006717_V3.PDF DOCUMENTS VIEW