Permit: TR-UTL-0825-01288
Permit Details
Status:
Complete
Type:
Right-of-Way (ROW) - Utility
Address:
1585 N YAVAPAI ST
Address NEW:
1585 N YAVAPAI ST
Apply Date:
08/07/2025
Applicant:
Tucson Electric Power
Description:
WO T157992 - Replacing existing pole and adding 2 new poles to feed new Duplex.
Permit Reviews
Permit Number - TR-UTL-0825-01288
Permit Status: Complete
Permit Description: WO T157992 - Replacing existing pole and adding 2 new poles to feed new Duplex.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/07/2025 | RIGHT-OF-WAY REVIEW v.1 | 09/02/2025 | REQUIRES RESUBMIT |
| 11/26/2025 | RIGHT-OF-WAY REVIEW v.2 | 11/26/2025 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-UTL-0825-01288
Permit Status: Complete
Permit Description: WO T157992 - Replacing existing pole and adding 2 new poles to feed new Duplex.
Total Outstanding Activity Conditions - 4
| Date | Name |
|---|---|
| 08/07/2025 | This project is located in an Archaeological Sensitivity Zone. An Archaeological Monitor hired by the permit applicant is required to be on-site during any digging, unless a waiver is issued. Monitoring reports are to be submitted to Historic Preservation Office, City of Tucson, P.O. Box 27210, Tucson, AZ 85726.** Please contact Historic Preservation Office at PDSDHistoric@tucsonaz.gov. |
| 08/07/2025 | PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. ** PAVEMENT PATCH TYPE SHALL BE IN CONFORMANCE TO THE CURRENT EDITION OF THE CITY OF TUCSON PUBLIC UTILITY ADMINISTRTIVE MANUAL **SIDEWALK CLOSED AHEAD SIGNS SHALL BE PLACED AT THE NEAREST ADA ACCESS RAMPS PER MUTCD CHAPTER 6D. |
| 08/07/2025 | Traffic Control set-up approved between 7AM - 5PM |
| 08/08/2025 | Pre-Activity Meeting Pre- activity meeting to be held 72 hrs in advance of work start with inspections.. PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING |
Completed Inspections
Permit Status: Complete
Permit Number: TR-UTL-0825-01288
Permit Description: WO T157992 - Replacing existing pole and adding 2 new poles to feed new Duplex.
Total Completed Inspections - 4
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/17/2025 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | ||
| 02/27/2026 | TRSP - ROW - Barricade - Setup/Routine | Passed | ||
| 02/27/2026 | TRSP - ROW - Backfill - Placement/Compaction | Passed | All work complete inspection not needed. Polls have been installed for power. | |
| 02/27/2026 | TRSP - ROW - Final | Passed | All work complete inspection not needed. Polls have been installed for power. |