Permit: TR-UTL-0825-01273
Permit Details
Status:
Needs Resubmittal
Type:
Right-of-Way (ROW) - Utility
Address:
601 W SANTA PAULA ST
Address NEW:
601 W SANTA PAULA ST
Apply Date:
08/06/2025
Applicant:
Ben Lozano / Border Traffic Safety LLC
Description:
Mission Manor Main Replacement Phase 1E - approx 3790LF of water main replacement with 41 service line replacements 11/12/25- in revision 12/02/25- Renew for 90 days as of 12/04/2025 new expiration date is 03/04/2026. //
Permit Reviews
Permit Number - TR-UTL-0825-01273
Permit Status: Needs resubmittal
Permit Description: Mission Manor Main Replacement Phase 1E - approx 3790LF of water main replacement with 41 service line replacements
11/12/25- in revision
12/02/25- Renew for 90 days as of 12/04/2025 new expiration date is 03/04/2026. //
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/29/2025 | RIGHT-OF-WAY REVIEW v.3 | 09/02/2025 | APPROVED |
| 08/25/2025 | RIGHT-OF-WAY REVIEW v.2 | 08/27/2025 | REQUIRES RESUBMIT |
| 01/02/2026 | RIGHT-OF-WAY REVIEW REVISION v.2 | 01/05/2026 | REQUIRES RESUBMIT |
| 08/06/2025 | RIGHT-OF-WAY REVIEW v.1 | 08/15/2025 | REQUIRES RESUBMIT |
| 11/04/2025 | RIGHT-OF-WAY REVIEW REVISION v.1 | 11/04/2025 | APPROVED |
| 11/12/2025 | RIGHT-OF-WAY REVIEW REVISION v.1 | 12/28/2025 | REQUIRES RESUBMIT |
| 01/07/2026 | RIGHT-OF-WAY REVIEW REVISION v.3 | 01/09/2026 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TR-UTL-0825-01273
Permit Status: Needs resubmittal
Permit Description: Mission Manor Main Replacement Phase 1E - approx 3790LF of water main replacement with 41 service line replacements
11/12/25- in revision
12/02/25- Renew for 90 days as of 12/04/2025 new expiration date is 03/04/2026. //
Total Outstanding Activity Conditions - 3
| Date | Name |
|---|---|
| 01/05/2026 | All excavations must be securely plated or backfilled at the end of each workday and during any period when the site is unattended. Plating shall be traffic-rated, flush with the surrounding surface, and properly secured to prevent movement and to maintain public safety |
| 08/06/2025 | Bus stop in the area, contact Joe Garcia, Sun Tran Dispatch, at 520-576-8726 at least 48-business hours prior to start of work for coordination. |
| 10/27/2025 | The following extended traffic control set-up times were approved: |
Outstanding Inspections
Permit Status: Needs Resubmittal
Permit Number: TR-UTL-0825-01273
Permite Description: Mission Manor Main Replacement Phase 1E - approx 3790LF of water main replacement with 41 service line replacements
11/12/25- in revision
12/02/25- Renew for 90 days as of 12/04/2025 new expiration date is 03/04/2026. //
Total Outstanding Inspections - 1
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/23/2026 | TRSP - ROW - Paving - Subgrade/removal/placement | N/A | Re-inspection required |
Completed Inspections
Permit Status: Needs Resubmittal
Permit Number: TR-UTL-0825-01273
Permit Description: Mission Manor Main Replacement Phase 1E - approx 3790LF of water main replacement with 41 service line replacements
11/12/25- in revision
12/02/25- Renew for 90 days as of 12/04/2025 new expiration date is 03/04/2026. //
Total Completed Inspections - 4
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/03/2025 | TRSP - ROW - SITE INSPECTION | Passed | ||
| 01/14/2026 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | ||
| 02/23/2026 | TRSP - ROW - Barricade - Setup/Routine | Passed | ||
| 02/23/2026 | TRSP - ROW - Backfill - Placement/Compaction | Passed |