Permit: TR-UTL-0824-01588
Permit Details
Status:
Complete
Type:
Right-of-Way (ROW) - Utility
Address:
7102 E PORTLAND DR
Address NEW:
7102 E PORTLAND DR
Apply Date:
08/22/2024
Applicant:
Desert Barricades LLC
Description:
WO T79303 - Memo 21-09 - Revision 1 (Sub-phase 1.3). Replace (18) transformers, (2) 100k cutouts, (2) J1 cabinets and replace 5,481’ of single-phase primary. No ground disturbance or civil work to be done, only replacing like for like UG equipment, and performing aerial maintenance.
Permit Reviews
Permit Number - TR-UTL-0824-01588
Permit Status: Complete
Permit Description: WO T79303 - Memo 21-09 - Revision 1 (Sub-phase 1.3). Replace (18) transformers, (2) 100k cutouts, (2) J1 cabinets and replace 5,481’ of single-phase primary. No ground disturbance or civil work to be done, only replacing like for like UG equipment, and performing aerial maintenance.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/23/2024 | RIGHT-OF-WAY REVIEW v.1 | 08/27/2024 | REQUIRES RESUBMIT |
| 08/28/2024 | RIGHT-OF-WAY REVIEW v.2 | 08/30/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-UTL-0824-01588
Permit Status: Complete
Permit Description: WO T79303 - Memo 21-09 - Revision 1 (Sub-phase 1.3). Replace (18) transformers, (2) 100k cutouts, (2) J1 cabinets and replace 5,481’ of single-phase primary. No ground disturbance or civil work to be done, only replacing like for like UG equipment, and performing aerial maintenance.
Total Outstanding Activity Conditions - 2
| Date | Name |
|---|---|
| 08/23/2024 | ** PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. ** PAVEMENT PATCH TYPE SHALL BE IN CONFORMANCE TO THE CURRENT EDITION OF THE CITY OF TUCSON PUBLIC UTILITY ADMINISTRTIVE MANUAL **SIDEWALK CLOSED AHEAD SIGNS SHALL BE PLACED AT THE NEAREST ADA ACCESS RAMPS PER MUTCD CHAPTER 6D. |
| 08/23/2024 | Traffic control set-up approved between 9AM - 3:30PM |
Completed Inspections
Permit Status: Complete
Permit Number: TR-UTL-0824-01588
Permit Description: WO T79303 - Memo 21-09 - Revision 1 (Sub-phase 1.3). Replace (18) transformers, (2) 100k cutouts, (2) J1 cabinets and replace 5,481’ of single-phase primary. No ground disturbance or civil work to be done, only replacing like for like UG equipment, and performing aerial maintenance.
Total Completed Inspections - 6
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/16/2024 | TRSP - ROW - Barricade - Setup/Routine | Passed | No barricade set up witnessed, confirmed with TEP job is complete | |
| 12/16/2024 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | No pre-con meeting held, confirmed with TEP job is complete | |
| 12/16/2024 | TRSP - ROW - Barricade Takedown | Passed | All traffic control elements removed, job complete | |
| 12/16/2024 | TRSP - ROW - Backfill - Placement/Compaction | Passed | Alleyway pedestals replaced, no trenching performed, job completed | |
| 12/16/2024 | TRSP - ROW - AERIAL INSTALLATION | Passed | Only riser connections made, aerial work approved | |
| 12/16/2024 | TRSP - ROW - Final | Passed | All other inspections completed, job closed |