Permit: TR-UTL-0824-01516
Permit Details
Status:
Complete
Type:
Right-of-Way (ROW) - Utility
Address:
5101 S 12TH AV
Address NEW:
5101 S 12TH AV
Apply Date:
08/14/2024
Applicant:
Richard Sanders
Description:
wo2426110 5101 s 12th av 15-13-01 nw corner. emergency valve and hydrant replacement in concrete 5lf/sc
Permit Reviews
Permit Number - TR-UTL-0824-01516
Permit Status: Complete
Permit Description: wo2426110 5101 s 12th av 15-13-01 nw corner. emergency valve and hydrant replacement in concrete 5lf/sc
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/14/2024 | RIGHT-OF-WAY REVIEW v.1 | 08/14/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-UTL-0824-01516
Permit Status: Complete
Permit Description: wo2426110 5101 s 12th av 15-13-01 nw corner. emergency valve and hydrant replacement in concrete 5lf/sc
Total Outstanding Activity Conditions - 4
| Date | Name |
|---|---|
| 08/14/2024 | Emergency – After the fact permit |
| 08/14/2024 | PAVEMENT MORATORIUM |
| 08/14/2024 | SIDEWALK |
| 08/14/2024 | Traffic Control set-up approved between 7AM - 5PM |
Outstanding Inspections
Permit Status: Complete
Permit Number: TR-UTL-0824-01516
Permite Description: wo2426110 5101 s 12th av 15-13-01 nw corner. emergency valve and hydrant replacement in concrete 5lf/sc
Total Outstanding Inspections - 2
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/13/2024 | TRSP - ROW - Concrete - Acceptance (Post-Pour) | N/A | Re-inspection required | concrete sidewalk not poured yet |
| 09/13/2024 | TRSP - ROW - Concrete - Subgrade/Forms (Pre-Pour) | N/A | Re-inspection required | temporary patch still in place, no forms yet |
Completed Inspections
Permit Status: Complete
Permit Number: TR-UTL-0824-01516
Permit Description: wo2426110 5101 s 12th av 15-13-01 nw corner. emergency valve and hydrant replacement in concrete 5lf/sc
Total Completed Inspections - 3
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/30/2024 | TRSP - ROW - Paving - Subgrade/removal/placement | Passed | no asphalt work needed | |
| 09/30/2024 | TRSP - ROW - Backfill - Placement/Compaction | Passed | backfill completed and temporary patch in place | |
| 10/16/2024 | TRSP - ROW - Final | Passed |