Permit: TR-UTL-0824-01439
Permit Details
Status:
Complete
Type:
Right-of-Way (ROW) - Utility
Address:
3734 S AVENIDA DE LAS PALMAS
Address NEW:
3734 S AVENIDA DE LAS PALMAS
Apply Date:
08/01/2024
Applicant:
Chelsey Bolinger
Description:
P.067197F (KAHNA) – BORE 5,022' & TRENCH 64’ TO PLACE CTL CONDUIT & FIBER CABLE. PLACE (33) HANDHOLES & (9) PEDESTALS.
Permit Reviews
Permit Number - TR-UTL-0824-01439
Permit Status: Complete
Permit Description: P.067197F (KAHNA) – BORE 5,022' & TRENCH 64’ TO PLACE CTL CONDUIT & FIBER CABLE. PLACE (33) HANDHOLES & (9) PEDESTALS.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/01/2024 | RIGHT-OF-WAY REVIEW v.1 | 08/05/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-UTL-0824-01439
Permit Status: Complete
Permit Description: P.067197F (KAHNA) – BORE 5,022' & TRENCH 64’ TO PLACE CTL CONDUIT & FIBER CABLE. PLACE (33) HANDHOLES & (9) PEDESTALS.
Total Outstanding Activity Conditions - 8
| Date | Name |
|---|---|
| 08/02/2024 | Alley must be restored to existing or better condition. Alley surface must be graded and compacted to City Standards and Specifications for Public Improvements and existing drainage patterns must be restored and maintained. Any disturbed gravel must be replaced. |
| 08/02/2024 | BUS STOP IN THE AREA, CONTACT SUN TRAN DISPATCH, AT 520-206-8934 AT LEAST 48-BUSINESS HOURS PRIOR TO START OF WORK FOR COORDINATION. |
| 08/02/2024 | Your project work requires that you contact City of Tucson Environmental Services Department (520-791-3171) at least 24 hours prior to closing any street or alley. |
| 08/02/2024 | Traffic Control set-up approved between 7AM - 5PM |
| 08/02/2024 | Traffic control set-up approved between 9AM - 3:30PM |
| 08/02/2024 | Pavement Patch type Shall Be in conformance to the current edition of the City of Tucson Public Utility Administrative Manual. |
| 08/02/2024 | PEDESTRIAN ACCESS MUST BE PROVIDED AND MAINTIANED PER MUTCD CHAPTER 6D. FIELD ADJUSTMENTS MAY BE REQUIRED. SIDEWALK CLOSED AHEAD SIGNS SHALL BE PLACED AT THE NEAREST ADA ACCESS RAMPS PER MUTCD CHAPTER 6D. REPLACE/REPAIR SIDEWALK PANELS PER PAG STANDARD DETAIL 200\206 |
| 08/02/2024 | Prop 411 project work area, Contact Nick Germanos at Nick.Germanos@tucsonaz.gov or James Degrood at James.degrood@tucsonaz.gov prior to start of work |
Outstanding Inspections
Permit Status: Complete
Permit Number: TR-UTL-0824-01439
Permite Description: P.067197F (KAHNA) – BORE 5,022' & TRENCH 64’ TO PLACE CTL CONDUIT & FIBER CABLE. PLACE (33) HANDHOLES & (9) PEDESTALS.
Total Outstanding Inspections - 5
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/13/2025 | TRSP - ROW - Barricade - Setup/Routine | N/A | Complete (Recurring) | alleyway closures in place |
| 02/17/2025 | TRSP - ROW - Paving - Subgrade/removal/placement | N/A | Not Ready | Paving still underway, road plate present at Avenida and Escalante intersection |
| 02/17/2025 | TRSP - ROW - Barricade Takedown | N/A | Not Ready | Barricades still in place for conduit |
| 02/17/2025 | TRSP - ROW - Backfill - Placement/Compaction | N/A | Not Ready | areas of conduit run still open |
| 02/17/2025 | TRSP - ROW - Final | N/A | Not Ready | Permit work still in progress |
Completed Inspections
Permit Status: Complete
Permit Number: TR-UTL-0824-01439
Permit Description: P.067197F (KAHNA) – BORE 5,022' & TRENCH 64’ TO PLACE CTL CONDUIT & FIBER CABLE. PLACE (33) HANDHOLES & (9) PEDESTALS.
Total Completed Inspections - 4
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/13/2025 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | Completed pre-con meeting with permit E on 11/7 | |
| 02/17/2025 | TRSP - ROW - Concrete - Acceptance (Post-Pour) | Passed | Grades and joints checked and approved | |
| 02/17/2025 | TRSP - ROW - Concrete - Subgrade/Forms (Pre-Pour) | Passed | Pre-pour not witnessed, sidewalk and curb replacement completed | |
| 06/04/2025 | TRSP - ROW - Final | Passed | Work completed under new permit tr-utl-0225-00278 |