Permit: TR-UTL-0726-01184
Permit Details
Status:
Needs Resubmittal
Type:
Right-of-Way (ROW) - Utility
Address:
654 W MABEL ST
Address NEW:
654 W MABEL ST
Apply Date:
07/17/2026
Applicant:
ANGEL MORALES
Description:
P.348986A Overbuild Bore 335' and trench 18' to place conduit and fiber cable Place 4461' of aerial fiber cable
Permit Reviews
Permit Number - TR-UTL-0726-01184
Permit Status: Needs resubmittal
Permit Description: P.348986A Overbuild
Bore 335' and trench 18' to place conduit and fiber cable
Place 4461' of aerial fiber cable
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/17/2026 | RIGHT-OF-WAY REVIEW v.1 | 08/24/2026 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TR-UTL-0726-01184
Permit Status: Needs resubmittal
Permit Description: P.348986A Overbuild
Bore 335' and trench 18' to place conduit and fiber cable
Place 4461' of aerial fiber cable
Total Outstanding Activity Conditions - 7
| Date | Name |
|---|---|
| 07/22/2026 | This project is located in an Archaeological Sensitivity Zone. An Archaeological Monitor hired by the permit applicant is required to be on-site during any digging, unless a waiver is issued. Monitoring reports are to be submitted to Historic Preservation Office at PDSDHistoric@tucsonaz.gov. |
| 07/22/2026 | CONTACT SUN TRAN DISPATCH, AT 520-206-8934 AT LEAST 48-BUSINESS HOURS PRIOR TO START OF WORK FOR COORDINATION WITH jose.garcia@tucsonaz.gov.. Due to the presence of a bus stop in the area, the contractor is required to contact Joe Garcia, Sun Tran Dispatch, at 520-576-8726 no less than 48 business hours before beginning work to coordinate impacts. |
| 07/22/2026 | Alley must be restored to existing or better condition. Alley surface must be graded and compacted to City Standards and Specifications for Public Improvements and existing drainage patterns must be restored and maintained. Any disturbed gravel must be replaced. |
| 07/22/2026 | Notify in writing at least 5 working days before work begins, any businesses, residences and public transit routes affected by your temporary traffic control. PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. |
| 07/22/2026 | Pre- activity/construction meeting with City inspectors to be held 72 hours in advance of work start. Please request Inspections in your permit portal on TDC Online. |
| 07/22/2026 | Traffic control set-up approved between 9AM - 3:30PM |
| 07/22/2026 | Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area. |