Permit: TR-UTL-0726-01167
Permit Details
Status:
Inspections Complete
Type:
Right-of-Way (ROW) - Utility
Address:
6355 S FONTANA AV
Address NEW:
6355 S FONTANA AV
Apply Date:
07/15/2026
Applicant:
Cox Communications
Description:
PRJ318961-1 Cox to bore 143' for CATV system tie
Permit Reviews
Permit Number - TR-UTL-0726-01167
Permit Status: Inspections complete
Permit Description: PRJ318961-1 Cox to bore 143' for CATV system tie
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/15/2026 | RIGHT-OF-WAY REVIEW v.1 | 08/03/2026 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-UTL-0726-01167
Permit Status: Inspections complete
Permit Description: PRJ318961-1 Cox to bore 143' for CATV system tie
Total Outstanding Activity Conditions - 5
| Date | Name |
|---|---|
| 07/16/2026 | Alley must be restored to existing or better condition. Alley surface must be graded and compacted to City Standards and Specifications for Public Improvement and existing drainage patterns must be restored and maintained. Any disturbed gravel must be replaced. |
| 07/16/2026 | Traffic control set-up approved between 9AM - 3:30PM |
| 07/16/2026 | Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area. |
| 07/16/2026 | Pre- activity/construction meeting with City inspectors to be held 72 hours in advance of work start. Please request Inspections in your permit portal on TDC Online. |
| 07/16/2026 | PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: TR-UTL-0726-01167
Permit Description: PRJ318961-1 Cox to bore 143' for CATV system tie
Total Completed Inspections - 4
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/22/2026 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | ||
| 10/06/2026 | TRSP - ROW - Barricade - Setup/Routine | Passed | ||
| 10/06/2026 | TRSP - ROW - Backfill - Placement/Compaction | Passed | ||
| 10/06/2026 | TRSP - ROW - Final | Passed |