Permit: TR-UTL-0725-01155
Permit Details
Status:
Complete
Type:
Right-of-Way (ROW) - Utility
Address:
1650 E 9TH ST
Address NEW:
1650 E 9TH ST
Apply Date:
07/18/2025
Applicant:
ANGEL MORALES
Description:
P.327534 - BORE 545', TRENCH 2', DIG 5 PITS, PLACE 2 NEW HHs(HH 1899 & HH2249) , REMOVE & REPLACE 2 SQFT OF ASPHALT, AND ACCESS EXISTING MH 7021, HH 1701, & LUMEN PED FOR SPLICING
Permit Reviews
Permit Number - TR-UTL-0725-01155
Permit Status: Complete
Permit Description: P.327534 - BORE 545', TRENCH 2', DIG 5 PITS, PLACE 2 NEW HHs(HH 1899 & HH2249) , REMOVE & REPLACE 2 SQFT OF ASPHALT, AND ACCESS EXISTING MH 7021, HH 1701, & LUMEN PED FOR SPLICING
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/30/2025 | RIGHT-OF-WAY REVIEW v.1 | 07/31/2025 | REQUIRES RESUBMIT |
| 07/31/2025 | RIGHT-OF-WAY REVIEW v.2 | 08/01/2025 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-UTL-0725-01155
Permit Status: Complete
Permit Description: P.327534 - BORE 545', TRENCH 2', DIG 5 PITS, PLACE 2 NEW HHs(HH 1899 & HH2249) , REMOVE & REPLACE 2 SQFT OF ASPHALT, AND ACCESS EXISTING MH 7021, HH 1701, & LUMEN PED FOR SPLICING
Total Outstanding Activity Conditions - 2
| Date | Name |
|---|---|
| 07/30/2025 | PRE-CON/PAVEMENT/SIDEWALK |
| 07/30/2025 | Traffic Control set-up approved between 7AM - 5PM |
Completed Inspections
Permit Status: Complete
Permit Number: TR-UTL-0725-01155
Permit Description: P.327534 - BORE 545', TRENCH 2', DIG 5 PITS, PLACE 2 NEW HHs(HH 1899 & HH2249) , REMOVE & REPLACE 2 SQFT OF ASPHALT, AND ACCESS EXISTING MH 7021, HH 1701, & LUMEN PED FOR SPLICING
Total Completed Inspections - 5
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/11/2025 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | ||
| 08/28/2025 | TRSP - ROW - Barricade - Setup/Routine | Passed | ||
| 08/28/2025 | TRSP - ROW - Backfill - Placement/Compaction | Passed | ||
| 09/19/2025 | TRSP - ROW - Barricade Takedown | Passed | ||
| 09/19/2025 | TRSP - ROW - Final | Passed |