Permit: TR-UTL-0725-01091
Permit Details
Status:
Complete
Type:
Right-of-Way (ROW) - Utility
Address:
6719 E 17TH ST
Address NEW:
6719 E 17TH ST
Apply Date:
07/08/2025
Applicant:
Alexander Bellmore
Description:
Replacement project - Approx. 1,322' of boring under dirt with an approx. 479' trench in pavement. Crews working along 17th St and Mann Ave and in the alleys north and south of 17th St.
Permit Reviews
Permit Number - TR-UTL-0725-01091
Permit Status: Complete
Permit Description: Replacement project - Approx. 1,322' of boring under dirt with an approx. 479' trench in pavement. Crews working along 17th St and Mann Ave and in the alleys north and south of 17th St.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/09/2025 | RIGHT-OF-WAY REVIEW v.1 | 07/09/2025 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-UTL-0725-01091
Permit Status: Complete
Permit Description: Replacement project - Approx. 1,322' of boring under dirt with an approx. 479' trench in pavement. Crews working along 17th St and Mann Ave and in the alleys north and south of 17th St.
Total Outstanding Activity Conditions - 4
| Date | Name |
|---|---|
| 07/09/2025 | ** PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. ** PAVEMENT PATCH TYPE SHALL BE IN CONFORMANCE TO THE CURRENT EDITION OF THE CITY OF TUCSON PUBLIC UTILITY ADMINISTRTIVE MANUAL **SIDEWALK CLOSED AHEAD SIGNS SHALL BE PLACED AT THE NEAREST ADA ACCESS RAMPS PER MUTCD CHAPTER 6D. |
| 07/09/2025 | Pre-Activity Meeting Pre- activity meeting to be held 72 hrs in advance of work start with inspections.. PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. |
| 07/09/2025 | Traffic Control set-up approved between 7AM - 5PM |
| 07/09/2025 | Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area. |
Completed Inspections
Permit Status: Complete
Permit Number: TR-UTL-0725-01091
Permit Description: Replacement project - Approx. 1,322' of boring under dirt with an approx. 479' trench in pavement. Crews working along 17th St and Mann Ave and in the alleys north and south of 17th St.
Total Completed Inspections - 4
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/30/2025 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | ||
| 09/24/2025 | TRSP - ROW - Barricade - Setup/Routine | Passed | ||
| 09/25/2025 | TRSP - ROW - Backfill - Placement/Compaction | Passed | ||
| 10/20/2025 | TRSP - ROW - Final | Passed |