Permit Details

Status:
Complete
Type:
Right-of-Way (ROW) - Utility
Address NEW:
2021 S TREE MOSS AV
Apply Date:
07/29/2024
Applicant:
Chelsey Bolinger
Description:
P.067193F KAHNA – BORE 3,176' & TRENCH 34’ TO PLACE CTL CONDUIT & FIBER CABLE. PLACE (15) HANDHOLES & (10) PEDESTALS.

Permit Reviews

Permit Number - TR-UTL-0724-01402
Permit Status: Complete
Permit Description: P.067193F KAHNA – BORE 3,176' & TRENCH 34’ TO PLACE CTL CONDUIT & FIBER CABLE. PLACE (15) HANDHOLES & (10) PEDESTALS.
Start Date Submittal Complete Date Status  
07/30/2024 RIGHT-OF-WAY REVIEW v.1 08/02/2024 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TR-UTL-0724-01402
Permit Status: Complete
Permit Description: P.067193F KAHNA – BORE 3,176' & TRENCH 34’ TO PLACE CTL CONDUIT & FIBER CABLE. PLACE (15) HANDHOLES & (10) PEDESTALS.
Total Outstanding Activity Conditions - 3
Date Name
07/30/2024 Alley must be restored to existing or better condition. Alley surface must be graded and compacted to City Standards and Specifications for Public Improvements and existing drainage patterns must be restored and maintained. Any disturbed gravel must be replaced.
07/30/2024 Your project work requires that you contact City of Tucson Environmental Services Department (520-791-3171) at least 24 hours prior to closing any street or alley.
07/30/2024 Traffic Control set-up approved between 7AM - 5PM

Outstanding Inspections

Permit Status: Complete
Permit Number: TR-UTL-0724-01402
Permite Description: P.067193F KAHNA – BORE 3,176' & TRENCH 34’ TO PLACE CTL CONDUIT & FIBER CABLE. PLACE (15) HANDHOLES & (10) PEDESTALS.
Total Outstanding Inspections - 4
Last Inspection Date Description Inspector Results Comments
11/15/2024 TRSP - ROW - Barricade - Setup/Routine N/A Complete (Recurring) no traffic control set up on 11/15, no crews working this area today, road plates and snow fencing still in place
11/12/2024 TRSP - ROW - Barricade Takedown N/A Not Ready awaiting permit extension request
11/12/2024 TRSP - ROW - Backfill - Placement/Compaction N/A Not Ready awaiting permit extension request
11/12/2024 TRSP - ROW - Final N/A Not Ready awaiting permit extension request

Completed Inspections

Permit Status: Complete
Permit Number: TR-UTL-0724-01402
Permit Description: P.067193F KAHNA – BORE 3,176' & TRENCH 34’ TO PLACE CTL CONDUIT & FIBER CABLE. PLACE (15) HANDHOLES & (10) PEDESTALS.
Total Completed Inspections - 5
Date Description Inspector Results Comments
11/05/2024 TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting Passed covered area in permit A pre con
02/12/2025 TRSP - ROW - Barricade - Setup/Routine Passed traffic control for alleyway closures has now been taken down, closures were consistent with work hours and flexible around services needing alleyway access(trash pick up)
02/12/2025 TRSP - ROW - Barricade Takedown Passed alleyways reopened, roadside devices removed. Single barricade on 34th is blocking sidewalk panel in need of replacement under permit G.
02/12/2025 TRSP - ROW - Backfill - Placement/Compaction Passed All backfill was performed in the alleyways in landscape areas using native soil, compacted to 85%, approved
02/12/2025 TRSP - ROW - Final Passed all prior inspections passed, job site clear of traffic control devices, job closed

Documents

File Name Document Type  
COT - TR - ROW PERMIT.PDF DOCUMENTS VIEW
P.067193F - CITY OF TUCSON AERIAL MAP - 07-29-2024_V1.PDF DOCUMENTS VIEW
P.067193F - CITY OF TUCSON PLANS - 07-29-2024_V1.PDF DOCUMENTS VIEW
P.067193F - CITY OF TUCSON TCP - 07-29-2024_V1.PDF DOCUMENTS VIEW