Permit: TR-UTL-0724-01296
Permit Details
Apply Date:
07/10/2024
Applicant:
Tucson Electric Power
Description:
WO 6363790. TEP to replace 8 poles and 50’ of underground secondary cable from New Pole to Existing Pedestal. Trench approx. 4'x2'.
Permit Reviews
Permit Number - TR-UTL-0724-01296
Permit Status: Complete
Permit Description: WO 6363790. TEP to replace 8 poles and 50’ of underground secondary cable from New Pole to Existing Pedestal. Trench approx. 4'x2'.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/11/2024 | RIGHT-OF-WAY REVIEW v.1 | 08/09/2024 | REQUIRES RESUBMIT |
| 08/12/2024 | RIGHT-OF-WAY REVIEW v.2 | 08/16/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-UTL-0724-01296
Permit Status: Complete
Permit Description: WO 6363790. TEP to replace 8 poles and 50’ of underground secondary cable from New Pole to Existing Pedestal. Trench approx. 4'x2'.
Total Outstanding Activity Conditions - 6
| Date | Name |
|---|---|
| 07/11/2024 | Traffic Control set-up approved between 7AM - 5PM |
| 08/12/2024 | Alley must be restored to existing or better condition. Alley surface must be graded and compacted to City Standards and Specifications for Public Improvements and existing drainage patterns must be restored and maintained. Any disturbed gravel must be replaced. |
| 08/12/2024 | Your project work requires that you contact City of Tucson Environmental Services Department (520-791-3171) at least 24 hours prior to closing any street or alley. |
| 08/12/2024 | PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. |
| 08/12/2024 | Pavement Patch type Shall Be in conformance to the current edition of the City of Tucson Public Utility Administrative Manual. |
| 08/15/2024 | AD Waiver provided. However, if any archaeological materials are encountered during construction, all ground disturbing activities must cease in the immediate vicinity of the discovery, and the Tucson Historic Preservation Office must be contacted to assess the find. |
Conditions
Permit Number - TR-UTL-0724-01296
Permit Status: Complete
Permit Description: WO 6363790. TEP to replace 8 poles and 50’ of underground secondary cable from New Pole to Existing Pedestal. Trench approx. 4'x2'.
| Date | Description | Comments |
|---|---|---|
| 07/11/2024 | This project is located in an Archaeological Sensitivity Zone. An Archaeological Monitor hired by the permit applicant is required to be on-site during any digging, unless a waiver is issued. Monitoring reports are to be submitted to Historic Preservation Office, City of Tucson, P.O. Box 27210, Tucson, AZ 85726.** Please contact Jodie Brown at Jodie.Brown@tucsonaz.gov with any questions. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TR-UTL-0724-01296
Permite Description: WO 6363790. TEP to replace 8 poles and 50’ of underground secondary cable from New Pole to Existing Pedestal. Trench approx. 4'x2'.
Total Outstanding Inspections - 1
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/22/2025 | TRSP - ROW - Final | N/A | Re-inspection required |
Completed Inspections
Permit Status: Complete
Permit Number: TR-UTL-0724-01296
Permit Description: WO 6363790. TEP to replace 8 poles and 50’ of underground secondary cable from New Pole to Existing Pedestal. Trench approx. 4'x2'.
Total Completed Inspections - 6
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/25/2024 | TRSP - ROW - Barricade - Setup/Routine | Passed | ||
| 11/25/2024 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | ||
| 11/25/2024 | TRSP - ROW - Barricade Takedown | Passed | ||
| 11/25/2024 | TRSP - ROW - Backfill - Placement/Compaction | Passed | ||
| 11/25/2024 | TRSP - ROW - AERIAL INSTALLATION | Passed | ||
| 10/12/2026 | TRSP - ROW - Final | Passed |