Permit Details

Status:
Complete
Type:
Right-of-Way (ROW) - Utility
Address:
2535 E 7TH ST
Address NEW:
2535 E 7TH ST
Apply Date:
07/26/2023
Applicant:
National Barricade LLC.
Description:
EXCAVATING A 60X3 TRENCH AT 2535 E 7TH ST TO REPLACE GAS SERVICE IN ROW IN ASPHALT, CONCRETE AND DIRT. TRENCH WILL BE LOCATED APPROX 25' EAST OF WEST P/L AND 1' NORTH OF SIDEWALK

Permit Reviews

Permit Number - TR-UTL-0723-02118
Permit Status: Complete
Permit Description: EXCAVATING A 60X3 TRENCH AT 2535 E 7TH ST TO REPLACE GAS SERVICE IN ROW IN ASPHALT, CONCRETE AND DIRT. TRENCH WILL BE LOCATED APPROX 25' EAST OF WEST P/L AND 1' NORTH OF SIDEWALK
Start Date Submittal Complete Date Status  
07/26/2023 RIGHT-OF-WAY REVIEW v.1 07/26/2023 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TR-UTL-0723-02118
Permit Status: Complete
Permit Description: EXCAVATING A 60X3 TRENCH AT 2535 E 7TH ST TO REPLACE GAS SERVICE IN ROW IN ASPHALT, CONCRETE AND DIRT. TRENCH WILL BE LOCATED APPROX 25' EAST OF WEST P/L AND 1' NORTH OF SIDEWALK
Total Outstanding Activity Conditions - 2
Date Name
07/26/2023 7th St is under a pavement cut moratorium and additional pavement repairs may be required, schedule a preactivity meeting with DTM Inspection. A 2" mill and inlay, with PAG Mix #2 (PG-76-22 TR+) will be required for the entire width of the impacted lanes and extend 25' on each side of the trench. All pavement striping must be restored in kind.
07/26/2023 Traffic Control set-up approved between 7AM - 5PM

Completed Inspections

Permit Status: Complete
Permit Number: TR-UTL-0723-02118
Permit Description: EXCAVATING A 60X3 TRENCH AT 2535 E 7TH ST TO REPLACE GAS SERVICE IN ROW IN ASPHALT, CONCRETE AND DIRT. TRENCH WILL BE LOCATED APPROX 25' EAST OF WEST P/L AND 1' NORTH OF SIDEWALK
Total Completed Inspections - 2
Date Description Inspector Results Comments
08/03/2023 TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting Passed
08/21/2024 TRSP - ROW - Notice of Completion Passed

Documents

File Name Document Type  
COT - TR - ROW PERMIT.PDF DOCUMENTS VIEW
2535 E 7TH ST TCP_V1.PDF DOCUMENTS VIEW
2535 E 7TH ST_V1.PDF DOCUMENTS VIEW