Status:
In Review
Type:
Right-of-Way (ROW) - Utility
Apply Date:
06/29/2026
Applicant:
Garcia David
Description:
MMR Fiber - SEGMENT 1 (Plan Phase 1) - This job (2)2" AND (4)7-WAY HDPE CONDUITS ALONG N Silverbell Rd. METHOD OF CONSTRUCTION TO BE DIRECTIONAL BORING AND/OR DIGGING/TRENCHING DEPENDING ON AREA AND ENGINEERING DRAWINGS. POSSIBLE PITS AND PLACING HANDHOLES. FIBER CABLE TO BE PLACED IN CONDUIT LOOPING INTO HANDHOLE. (DTM Note-- Refer to Attachments for Related Permit from Contractor)

Permit Reviews

Permit Number - TR-UTL-0626-01067
Permit Status: In review
Permit Description: MMR Fiber - SEGMENT 1 (Plan Phase 1) - This job (2)2" AND (4)7-WAY HDPE CONDUITS ALONG N Silverbell Rd. METHOD OF CONSTRUCTION TO BE DIRECTIONAL BORING AND/OR DIGGING/TRENCHING DEPENDING ON AREA AND ENGINEERING DRAWINGS. POSSIBLE PITS AND PLACING HANDHOLES. FIBER CABLE TO BE PLACED IN CONDUIT LOOPING INTO HANDHOLE. (DTM Note-- Refer to Attachments for Related Permit from Contractor)
Start Date Submittal Complete Date Status  
07/28/2026 RIGHT-OF-WAY REVIEW v.5 N/A IN REVIEW Review Details
07/07/2026 RIGHT-OF-WAY REVIEW v.2 N/A REQUIRES RESUBMIT Review Details
07/16/2026 RIGHT-OF-WAY REVIEW v.4 07/20/2026 REQUIRES RESUBMIT Review Details
06/29/2026 RIGHT-OF-WAY REVIEW v.1 N/A REQUIRES RESUBMIT Review Details
07/09/2026 RIGHT-OF-WAY REVIEW v.3 07/13/2026 REQUIRES RESUBMIT Review Details

Outstanding Activity Conditions

Permit Number - TR-UTL-0626-01067
Permit Status: In review
Permit Description: MMR Fiber - SEGMENT 1 (Plan Phase 1) - This job (2)2" AND (4)7-WAY HDPE CONDUITS ALONG N Silverbell Rd. METHOD OF CONSTRUCTION TO BE DIRECTIONAL BORING AND/OR DIGGING/TRENCHING DEPENDING ON AREA AND ENGINEERING DRAWINGS. POSSIBLE PITS AND PLACING HANDHOLES. FIBER CABLE TO BE PLACED IN CONDUIT LOOPING INTO HANDHOLE. (DTM Note-- Refer to Attachments for Related Permit from Contractor)
Total Outstanding Activity Conditions - 7
Date Name
07/09/2026 ADOT permits will be required for work in and Traffic Control within ADOT ROW
07/09/2026 This project is located in an Archaeological Sensitivity Zone. An Archaeological Monitor hired by the permit applicant is required to be on-site during any digging, unless a waiver is issued. Monitoring reports are to be submitted to the Historic Preservation Office, City of Tucson, PO BOX 27210, Tucson AZ 85726...***Please contact Historic Preservation Office at PDSDHistoric@tucsonaz.gov.
07/09/2026 Approved for Work within City of Tucson Right of Way Only. Pima Couty permits will be required for work in and Traffic Control within Pima ROW
07/09/2026 Traffic control set-up approved between 9AM - 3:30PM
07/09/2026 Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area.
07/09/2026 Pre- activity/construction meeting with City inspectors to be held 72 hours in advance of work start. Please request Inspections in your permit portal on TDC Online.
07/09/2026 PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING.