Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
Inspections
Type:
Right-of-Way (ROW) - Utility
Address:
4581 S 12TH AV
Address NEW:
4581 S 12TH AV
Apply Date:
06/11/2026
Applicant:
Arnulfo Quiroz
Description:
WO T168450 - TEP TO REPLACE 6 POLES AND INSTALL 2 NEW POLES WITH 2 ANCHORS

Permit Reviews

Permit Number - TR-UTL-0626-00972
Permit Status: Inspections
Permit Description: WO T168450 - TEP TO REPLACE 6 POLES AND INSTALL 2 NEW POLES WITH 2 ANCHORS
Start Date Submittal Complete Date Status  
06/11/2026 RIGHT-OF-WAY REVIEW v.1 06/12/2026 REQUIRES RESUBMIT Review Details
06/16/2026 RIGHT-OF-WAY REVIEW v.2 06/23/2026 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TR-UTL-0626-00972
Permit Status: Inspections
Permit Description: WO T168450 - TEP TO REPLACE 6 POLES AND INSTALL 2 NEW POLES WITH 2 ANCHORS
Total Outstanding Activity Conditions - 8
Date Name
06/11/2026 Traffic control set-up approved between 9AM - 3:30PM
06/23/2026 Bike Lane Access and Accommodation 1) Posted Speeds 30 Mph or Less โ€“ Less than 14 lane - Use of the R4-11 alone is acceptable and preferred over Share The Road sign - 2) Posted Speeds 30 Mph or less โ€“ greater than 14 lane - Use of Share The Road sign is preferred 3) Posted Speeds 30 Mph or More โ€“ Any Lane Size - Provide a reasonable alternative for cyclists, such as a paved path, space behind barricades, or bike detour. Acceptable to direct cyclists to the sidewalk when properly signed depending on conditions 4) Bike lane to be maintained within Traffic Control closure and Share may Pedestrian detour path with proper R9-6 Sign.
06/23/2026 Pre-Activity Meeting w/Inspections Pre- activity/construction meeting with City inspectors to be held 72 hours in advance of work start. Please request Inspections in your permit portal on TDC Online. PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING.
06/23/2026 Lane closures shall only be permitted during active work operations. At the end of each workday, the contractor shall remove all traffic control devices and reopen the roadway, bike lanes, and sidewalks to normal operation. Twenty-four (24) hour lane closures are not permitted unless specifically approved by the City. Traffic Control Devices shall not be stored in the bike lane or sidewalk
06/23/2026 Notify in writing at least 5 working days before work begins, any businesses, residences and public transit routes affected by your temporary traffic control. PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING.
06/23/2026 Pedestrian Access & Sidewalk PEDESTRIAN ACCESS MUST BE PROVIDED AND MAINTIANED PER MUTCD CHAPTER 6D. FIELD ADJUSTMENTS MAY BE REQUIRED. REPLACE/REPAIR SIDEWALK PANELS PER PAG STANDARD DETAIL 200\206 . PEDESTRIAN DETOUR ROUTE ON SAME SIDE OF RIGHT OF WAY TO BE PROVIDED. PER CITY CODE AND POLICY. Refer to MUTCD Chapter 6 Figure 6P-28, and 6K figure 6K-2. Refer to COT Utility manual Page 41 - 42 Refer to COT 2015 Addition to the MUTCD section 14
06/23/2026 No pedestrian detour is proposed; therefore, the sidewalk shall remain open and ADA-compliant at all times during construction. Worker-assisted pedestrian access does not constitute a pedestrian detour and shall not require pedestrians to leave the designated pedestrian path. If the sidewalk cannot be maintained in an open and ADA-compliant condition, an approved pedestrian detour shall be implemented prior to any sidewalk closure.
06/23/2026 Sec. 25-5. Permit expiration. A permit shall expire for work not started within thirty (30) days or completed within sixty (60) days after issuance of a permit, and a new permit shall be required before beginning or completing the work. (Ord. No. 2657, ยง 1, 10-19-64)

Completed Inspections

Permit Status: Inspections
Permit Number: TR-UTL-0626-00972
Permit Description: WO T168450 - TEP TO REPLACE 6 POLES AND INSTALL 2 NEW POLES WITH 2 ANCHORS
Total Completed Inspections - 1
Date Description Inspector Results Comments
06/26/2026 TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting Passed

Documents

File Name Document Type  
COT - TR - ROW PERMIT (SSRS).PDF DOCUMENTS VIEW
REVISED MAP FOR PERMIT_V2.PDF DOCUMENTS VIEW
REVISED TCP_V2.PDF DOCUMENTS VIEW