Permit: TR-UTL-0626-00971
Permit Details
Status:
Inspections
Type:
Right-of-Way (ROW) - Utility
Address:
1218 W IRVINGTON RD
Address NEW:
1218 W IRVINGTON RD
Apply Date:
06/11/2026
Applicant:
Brittany West
Description:
begin phase 4 part 1 at the end of phase 3. Hang 2,180ft of new strand and 144ct fiber along proposed path.begin pahse 4 part 2 at the end of part 1. hang new strand and new 144ct fiber for 2,275ft 08/21/2026 - Request for 30 Day Renewal as of 09/05/2026 Permit Renewal Notice Effective July 1, 2026, the Mayor and Council approved and implemented a new fee structure and updated application requirements for right-of-way permits. Permits issued prior to July 1, 2026, under the previous fee structure, are eligible for one final renewal for a maximum of 30 days. The previous 60- and 90-day renewal options are no longer available. If work extends beyond the 30-day renewal period, a new permit application must be submitted. The new application must comply with the current fee structure and include all required project information, including the actual number of days traffic control and/or lane closures will be in place (not the permit duration) and the length × width (L × W) of all pavement cuts.
Permit Reviews
Permit Number - TR-UTL-0626-00971
Permit Status: Inspections
Permit Description: begin phase 4 part 1 at the end of phase 3. Hang 2,180ft of new strand and 144ct fiber along proposed path.begin pahse 4 part 2 at the end of part 1. hang new strand and new 144ct fiber for 2,275ft
08/21/2026 - Request for 30 Day Renewal as of 09/05/2026
Permit Renewal Notice
Effective July 1, 2026, the Mayor and Council approved and implemented a new fee structure and updated application requirements for right-of-way permits.
Permits issued prior to July 1, 2026, under the previous fee structure, are eligible for one final renewal for a maximum of 30 days. The previous 60- and 90-day renewal options are no longer available.
If work extends beyond the 30-day renewal period, a new permit application must be submitted. The new application must comply with the current fee structure and include all required project information, including the actual number of days traffic control and/or lane closures will be in place (not the permit duration) and the length × width (L × W) of all pavement cuts.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/11/2026 | RIGHT-OF-WAY REVIEW v.1 | 06/22/2026 | REQUIRES RESUBMIT |
| 06/29/2026 | RIGHT-OF-WAY REVIEW v.2 | 08/03/2026 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-UTL-0626-00971
Permit Status: Inspections
Permit Description: begin phase 4 part 1 at the end of phase 3. Hang 2,180ft of new strand and 144ct fiber along proposed path.begin pahse 4 part 2 at the end of part 1. hang new strand and new 144ct fiber for 2,275ft
08/21/2026 - Request for 30 Day Renewal as of 09/05/2026
Permit Renewal Notice
Effective July 1, 2026, the Mayor and Council approved and implemented a new fee structure and updated application requirements for right-of-way permits.
Permits issued prior to July 1, 2026, under the previous fee structure, are eligible for one final renewal for a maximum of 30 days. The previous 60- and 90-day renewal options are no longer available.
If work extends beyond the 30-day renewal period, a new permit application must be submitted. The new application must comply with the current fee structure and include all required project information, including the actual number of days traffic control and/or lane closures will be in place (not the permit duration) and the length × width (L × W) of all pavement cuts.
Total Outstanding Activity Conditions - 6
| Date | Name |
|---|---|
| 06/15/2026 | ROW Permit is only allowed for work within City of Tucson Right of Way. |
| 06/15/2026 | Traffic Control set-up approved between 7AM - 5PM |
| 06/15/2026 | Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area. |
| 06/15/2026 | Pre- activity/construction meeting with City inspectors to be held 72 hours in advance of work start. Please request Inspections in your permit portal on TDC Online. |
| 06/15/2026 | Driveways and private property shall NOT be utilized without the owner’s consent. It is the contractor’s responsibility to negotiate use of private property. |
| 06/15/2026 | PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. |
Outstanding Inspections
Permit Status: Inspections
Permit Number: TR-UTL-0626-00971
Permite Description: begin phase 4 part 1 at the end of phase 3. Hang 2,180ft of new strand and 144ct fiber along proposed path.begin pahse 4 part 2 at the end of part 1. hang new strand and new 144ct fiber for 2,275ft
08/21/2026 - Request for 30 Day Renewal as of 09/05/2026
Permit Renewal Notice
Effective July 1, 2026, the Mayor and Council approved and implemented a new fee structure and updated application requirements for right-of-way permits.
Permits issued prior to July 1, 2026, under the previous fee structure, are eligible for one final renewal for a maximum of 30 days. The previous 60- and 90-day renewal options are no longer available.
If work extends beyond the 30-day renewal period, a new permit application must be submitted. The new application must comply with the current fee structure and include all required project information, including the actual number of days traffic control and/or lane closures will be in place (not the permit duration) and the length × width (L × W) of all pavement cuts.
Total Outstanding Inspections - 3
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| TRSP - ROW - Barricade - Setup/Routine | N/A | Requested | ||
| TRSP - ROW - AERIAL INSTALLATION | N/A | Requested | ||
| TRSP - ROW - Final | N/A | Requested |
Completed Inspections
Permit Status: Inspections
Permit Number: TR-UTL-0626-00971
Permit Description: begin phase 4 part 1 at the end of phase 3. Hang 2,180ft of new strand and 144ct fiber along proposed path.begin pahse 4 part 2 at the end of part 1. hang new strand and new 144ct fiber for 2,275ft
08/21/2026 - Request for 30 Day Renewal as of 09/05/2026
Permit Renewal Notice
Effective July 1, 2026, the Mayor and Council approved and implemented a new fee structure and updated application requirements for right-of-way permits.
Permits issued prior to July 1, 2026, under the previous fee structure, are eligible for one final renewal for a maximum of 30 days. The previous 60- and 90-day renewal options are no longer available.
If work extends beyond the 30-day renewal period, a new permit application must be submitted. The new application must comply with the current fee structure and include all required project information, including the actual number of days traffic control and/or lane closures will be in place (not the permit duration) and the length × width (L × W) of all pavement cuts.
Total Completed Inspections - 1
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/05/2026 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed |