Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
Inspections
Type:
Right-of-Way (ROW) - Utility
Address NEW:
7070 E TANQUE VERDE RD
Apply Date:
06/10/2026
Applicant:
Brittany West
Description:
Tie point wil be existing fiber airel case. Overlash 850' over 4 span. Rider down and install new vault.Bore 320' of 2" conduit at a depth of 3', run 320' of 48ct fiber. Place a new vault. Bore 70' of 2" conduit at a depth of 3', run 70' of 48ct fiber. Install new lock box. 09/02/26- denied extension due to no pre-activity meeting inspection was schedule.

Permit Reviews

Permit Number - TR-UTL-0626-00968
Permit Status: Inspections
Permit Description: Tie point wil be existing fiber airel case. Overlash 850' over 4 span. Rider down and install new vault.Bore 320' of 2" conduit at a depth of 3', run 320' of 48ct fiber. Place a new vault. Bore 70' of 2" conduit at a depth of 3', run 70' of 48ct fiber. Install new lock box. 09/02/26- denied extension due to no pre-activity meeting inspection was schedule.
Start Date Submittal Complete Date Status  
07/28/2026 RIGHT-OF-WAY REVIEW v.2 08/12/2026 APPROVED Review Details
06/10/2026 RIGHT-OF-WAY REVIEW v.1 N/A REQUIRES RESUBMIT Review Details

Outstanding Activity Conditions

Permit Number - TR-UTL-0626-00968
Permit Status: Inspections
Permit Description: Tie point wil be existing fiber airel case. Overlash 850' over 4 span. Rider down and install new vault.Bore 320' of 2" conduit at a depth of 3', run 320' of 48ct fiber. Place a new vault. Bore 70' of 2" conduit at a depth of 3', run 70' of 48ct fiber. Install new lock box. 09/02/26- denied extension due to no pre-activity meeting inspection was schedule.
Total Outstanding Activity Conditions - 5
Date Name
06/11/2026 Alley must be restored to existing or better condition. Alley surface must be graded and compacted to City Standards and Specifications for Public Improvement and existing drainage patterns must be restored and maintained. Any disturbed gravel must be replaced.
06/11/2026 BUS STOP IN THE AREA, CONTACT SUN TRAN DISPATCH, AT 520-206-8934 AT LEAST 48-BUSINESS HOURS PRIOR TO START OF WORK FOR COORDINATION.
06/11/2026 Traffic control set-up approved between 9AM - 3:30PM
06/11/2026 Pre- activity/construction meeting with City inspectors to be held 72 hours in advance of work start. Please request Inspections in your permit portal on TDC Online.
06/11/2026 PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING.

Completed Inspections

Permit Status: Inspections
Permit Number: TR-UTL-0626-00968
Permit Description: Tie point wil be existing fiber airel case. Overlash 850' over 4 span. Rider down and install new vault.Bore 320' of 2" conduit at a depth of 3', run 320' of 48ct fiber. Place a new vault. Bore 70' of 2" conduit at a depth of 3', run 70' of 48ct fiber. Install new lock box. 09/02/26- denied extension due to no pre-activity meeting inspection was schedule.
Total Completed Inspections - 2
Date Description Inspector Results Comments
10/19/2026 TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting Passed
10/19/2026 Passed

Documents

File Name Document Type  
COT - TR - ROW PERMIT (SSRS).PDF DOCUMENTS VIEW
DESIGN PLAN-JB0002525850_PERMIT MAP 2-C1_V1.PDF DOCUMENTS VIEW
TCP_V1.PDF DOCUMENTS VIEW