Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
Complete
Type:
Right-of-Way (ROW) - Utility
Address NEW:
3020 E PRESIDIO RD
Apply Date:
06/02/2026
Applicant:
Rene Villalobos
Description:
wo#3298716 3020 e presidio rd 14-13-32 ne relocate service north side of lot in dirt 6LF/sc

Permit Reviews

Permit Number - TR-UTL-0626-00933
Permit Status: Complete
Permit Description: wo#3298716 3020 e presidio rd 14-13-32 ne relocate service north side of lot in dirt 6LF/sc
Start Date Submittal Complete Date Status  
06/02/2026 RIGHT-OF-WAY REVIEW v.1 06/22/2026 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TR-UTL-0626-00933
Permit Status: Complete
Permit Description: wo#3298716 3020 e presidio rd 14-13-32 ne relocate service north side of lot in dirt 6LF/sc
Total Outstanding Activity Conditions - 4
Date Name
06/03/2026 Notify in writing at least 5 working days before work begins, any businesses, residences and public transit routes affected by your temporary traffic control. PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING.
06/03/2026 Pre- activity/construction meeting with City inspectors to be held 72 hours in advance of work start. Please request Inspections in your permit portal on TDC Online.
06/03/2026 Traffic Control set-up approved between 7AM - 5PM
06/03/2026 ANY NEW ASPHALT THAT IS DISTURBED WILL REQUIRE A 2” MILL AND OVERLAY FOR 25’ IN EACH DIRECTION FROM THE OUTSIDE OF THE CUT FOR ALL EFFECTED TRAVEL LANES.

Completed Inspections

Permit Status: Complete
Permit Number: TR-UTL-0626-00933
Permit Description: wo#3298716 3020 e presidio rd 14-13-32 ne relocate service north side of lot in dirt 6LF/sc
Total Completed Inspections - 4
Date Description Inspector Results Comments
07/20/2026 TRSP - ROW - Barricade - Setup/Routine Passed Inspection not needed Yes all removed all work looks to be completed utility owner did not respond to verify if further work needs to be done they will get a new permit and work and patching was done by a 411 project
07/20/2026 TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting Passed Inspection not needed Yes all removed all work looks to be completed utility owner did not respond to verify if further work needs to be done they will get a new permit and work and patching was done by a 411 project
07/20/2026 TRSP - ROW - Backfill - Placement/Compaction Passed Inspection not needed Yes all removed all work looks to be completed utility owner did not respond to verify if further work needs to be done they will get a new permit and work and patching was done by a 411 project
07/20/2026 TRSP - ROW - Final Passed Yes all removed all work looks to be completed utility owner did not respond to verify if further work needs to be done they will get a new permit and work and patching was done by a 411 project

Documents

File Name Document Type  
3020 E PRESIDIO RD_CSKETCH_V1.PDF DOCUMENTS VIEW
COT - TR - ROW PERMIT (SSRS).PDF DOCUMENTS VIEW