Permit Details

Status:
Complete
Type:
Right-of-Way (ROW) - Utility
Address:
3562 N TUCSON BL
Address NEW:
3562 N TUCSON BL
Apply Date:
06/02/2026
Applicant:
Brittany West
Description:
Place 1175' of new strand over 7 spans and run 1600' of fiber. Place new aerial splice case and storage. Place 1610' of new strand over 9 span and run 1610' of fiber. Place new aerial splice case and storage. Place 390' of new strand over 3 span and run 390' of fiber. Place storage.

Permit Reviews

Permit Number - TR-UTL-0626-00927
Permit Status: Complete
Permit Description: Place 1175' of new strand over 7 spans and run 1600' of fiber. Place new aerial splice case and storage. Place 1610' of new strand over 9 span and run 1610' of fiber. Place new aerial splice case and storage. Place 390' of new strand over 3 span and run 390' of fiber. Place storage.
Start Date Submittal Complete Date Status  
06/02/2026 RIGHT-OF-WAY REVIEW v.1 N/A REQUIRES RESUBMIT Review Details
07/06/2026 RIGHT-OF-WAY REVIEW v.2 07/10/2026 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TR-UTL-0626-00927
Permit Status: Complete
Permit Description: Place 1175' of new strand over 7 spans and run 1600' of fiber. Place new aerial splice case and storage. Place 1610' of new strand over 9 span and run 1610' of fiber. Place new aerial splice case and storage. Place 390' of new strand over 3 span and run 390' of fiber. Place storage.
Total Outstanding Activity Conditions - 5
Date Name
06/09/2026 BUS STOP IN THE AREA, CONTACT SUN TRAN DISPATCH, AT 520-206-8934 AT LEAST 48-BUSINESS HOURS PRIOR TO START OF WORK FOR COORDINATION.
06/09/2026 PRINCE RD IS UNDER A PAVEMENT MORATORIUM, ANY NEW ASPHALT THAT IS DISTURBED WILL REQUIRE A 2” MILL AND OVERLAY FOR 25’ IN EACH DIRECTION FROM THE OUTSIDE OF THE CUT FOR ALL EFFECTED TRAVEL LANES.
06/09/2026 Pre- activity/construction meeting with City inspectors to be held 72 hours in advance of work start. Please request Inspections in your permit portal on TDC Online.
06/09/2026 PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING.
06/09/2026 PLEASE SEE ATTACHMENTS FOR CONDITION ON STORM TO SHADE.

Completed Inspections

Permit Status: Complete
Permit Number: TR-UTL-0626-00927
Permit Description: Place 1175' of new strand over 7 spans and run 1600' of fiber. Place new aerial splice case and storage. Place 1610' of new strand over 9 span and run 1610' of fiber. Place new aerial splice case and storage. Place 390' of new strand over 3 span and run 390' of fiber. Place storage.
Total Completed Inspections - 4
Date Description Inspector Results Comments
07/23/2026 TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting Passed
08/13/2026 TRSP - ROW - Barricade - Setup/Routine Passed
08/13/2026 TRSP - ROW - AERIAL INSTALLATION Passed All work completed on this permit they're letting the rest expire till they start a new permit on the rest of their build. This permit is completed for the work they started.
08/13/2026 TRSP - ROW - Final Passed All work completed on this permit they're letting the rest expire till they start a new permit on the rest of their build. This permit is completed for the work they started.

Documents

File Name Document Type  
COT - TR - ROW PERMIT (SSRS).PDF DOCUMENTS VIEW
TCP REVISED_V2.PDF DOCUMENTS VIEW
JB0002192231_PERMIT MAP PHASE 6_V1.PDF DOCUMENTS VIEW