Permit: TR-UTL-0625-00978
Permit Details
Status:
Complete
Type:
Right-of-Way (ROW) - Utility
Address:
1141 N FALCON RIDGE DR
Address NEW:
1141 N FALCON RIDGE DR
Apply Date:
06/18/2025
Applicant:
Desert Barricades LLC
Description:
WO T129161 - TEP will be removing 1 pole in the ROW a 2'x2' hole 6' deep will be backfilled without sidewalk impact. Location of pole is located on the southside of Speedway Bl across from listed address.
Permit Reviews
Permit Number - TR-UTL-0625-00978
Permit Status: Complete
Permit Description: WO T129161 - TEP will be removing 1 pole in the ROW a 2'x2' hole 6' deep will be backfilled without sidewalk impact. Location of pole is located on the southside of Speedway Bl across from listed address.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/18/2025 | RIGHT-OF-WAY REVIEW v.1 | 06/21/2025 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-UTL-0625-00978
Permit Status: Complete
Permit Description: WO T129161 - TEP will be removing 1 pole in the ROW a 2'x2' hole 6' deep will be backfilled without sidewalk impact. Location of pole is located on the southside of Speedway Bl across from listed address.
Total Outstanding Activity Conditions - 4
| Date | Name |
|---|---|
| 06/18/2025 | Bus Stop / Route |
| 06/18/2025 | Traffic control set-up approved between 9AM - 3:30PM |
| 06/20/2025 | Pre-Activity Meeting Pre- activity meeting to be held 72 hrs in advance of work start with inspections.. PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. |
| 06/20/2025 | Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area. |
Completed Inspections
Permit Status: Complete
Permit Number: TR-UTL-0625-00978
Permit Description: WO T129161 - TEP will be removing 1 pole in the ROW a 2'x2' hole 6' deep will be backfilled without sidewalk impact. Location of pole is located on the southside of Speedway Bl across from listed address.
Total Completed Inspections - 4
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/04/2025 | TRSP - ROW - Barricade - Setup/Routine | Passed | ||
| 09/04/2025 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | ||
| 09/04/2025 | TRSP - ROW - Backfill - Placement/Compaction | Passed | ||
| 09/04/2025 | TRSP - ROW - Final | Passed |