Permit: TR-UTL-0625-00957
Permit Details
Status:
Inspections
Type:
Right-of-Way (ROW) - Utility
Address:
1151 N BELVEDERE AV
Address NEW:
1151 N BELVEDERE AV
Apply Date:
06/13/2025
Applicant:
Chelsey Bolinger
Description:
P.099166 (KAHNA) - BORE 1,087 & TRENCH 70’ TO PLACE CTL CONDUIT & FIBER CABLE. PLACE (1) FSAI CABINET, (16) HANDHOLES & PEDESTALS. OVERLASH 2,928’ OF AERIAL FIBER CABLE.
Permit Reviews
Permit Number - TR-UTL-0625-00957
Permit Status: Inspections
Permit Description: P.099166 (KAHNA) - BORE 1,087 & TRENCH 70’ TO PLACE CTL CONDUIT & FIBER CABLE. PLACE (1) FSAI CABINET, (16) HANDHOLES & PEDESTALS. OVERLASH 2,928’ OF AERIAL FIBER CABLE.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/13/2025 | RIGHT-OF-WAY REVIEW v.1 | 06/18/2025 | APPROVED |
| 10/03/2025 | RIGHT-OF-WAY REVIEW REVISION v.1 | 10/06/2025 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-UTL-0625-00957
Permit Status: Inspections
Permit Description: P.099166 (KAHNA) - BORE 1,087 & TRENCH 70’ TO PLACE CTL CONDUIT & FIBER CABLE. PLACE (1) FSAI CABINET, (16) HANDHOLES & PEDESTALS. OVERLASH 2,928’ OF AERIAL FIBER CABLE.
Total Outstanding Activity Conditions - 5
| Date | Name |
|---|---|
| 06/16/2025 | Pavement Moratorium |
| 06/16/2025 | Traffic Control set-up approved between 7AM - 5PM |
| 06/16/2025 | Traffic control set-up approved between 9AM - 3:30PM |
| 06/18/2025 | Bus Stop |
| 06/18/2025 | Pavement Moratorium |
Completed Inspections
Permit Status: Inspections
Permit Number: TR-UTL-0625-00957
Permit Description: P.099166 (KAHNA) - BORE 1,087 & TRENCH 70’ TO PLACE CTL CONDUIT & FIBER CABLE. PLACE (1) FSAI CABINET, (16) HANDHOLES & PEDESTALS. OVERLASH 2,928’ OF AERIAL FIBER CABLE.
Total Completed Inspections - 5
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/31/2025 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | ||
| 10/01/2025 | TRSP - ROW - Barricade - Setup/Routine | Passed | ||
| 10/01/2025 | TRSP - ROW - Barricade Takedown | Passed | ||
| 10/01/2025 | TRSP - ROW - Backfill - Placement/Compaction | Passed | ||
| 10/01/2025 | TRSP - ROW - Final | Passed |